Constant Velocity Half-Shaft & Joint

Product family: Front-Wheel CV Axles.

Flow: Axle shaft forge → Shaft Spline Roll → Tulip Bell Heat-Treat → Ball Cage Match & Grease → TPE Boot Clamp & Spin → Torque Angle & Imbalance → OEM Axle & Aftermarket

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Constant Velocity Half-Shaft & JointSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Axle shaft forge → Shaft Spline Roll (25.0 s) → Tulip Bell Heat-Treat (30.9 s) → Ball Cage Match & Grease (39.0 s) → TPE Boot Clamp & Spin (28.7 s) → Torque Angle & Imbalance (22.8 s) → OEM Axle & Aftermarket.SUPPLIERAxle shaftforgeI1.80 d1Shaft Spline RollC/T 25.0 sI1.40 d2Tulip BellHeat-TreatC/T 30.9 sI2.20 d3Ball Cage Match &GreaseC/T 39.0 sI1.10 d4TPE Boot Clamp &SpinC/T 28.7 sI0.80 d5Torque Angle &ImbalanceC/T 22.8 sI1.50 dCUSTOMEROEM Axle &Aftermarket2,200 / parts

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Shaft Spline Roll25.0 s45 min94%98.6%3,3003,960 (1.80 d)2,936
2. Tulip Bell Heat-Treat30.9 s38 min91%97.8%2,2003,080 (1.40 d)2,267
3. Ball Cage Match & Grease39.0 s65 min84%95.8%3,3004,840 (2.20 d)1,618
4. TPE Boot Clamp & Spin28.7 s15 min94%98.4%1,1002,420 (1.10 d)2,553
5. Torque Angle & Imbalance22.8 s10 min96%99.1%5501,760 (0.80 d)3,280

Key figures

Takt time
36.8 s
Lead time
8.80 d
Value-added time
146 s
Process cycle efficiency (PCE)
0.021%
Rolled throughput yield (RTY)
90.1%
Customer demand per day
2,200 parts
Line capacity per day
1,618 parts
Bottleneck
Ball Cage Match & Grease

Reading the bottleneck

The bottleneck is "Ball Cage Match & Grease": it can process 1,618 parts per day against a demand of 2,200 parts, so it falls short of demand by 26.5%. Once downtime and scrap are counted, its cycle time grows from 39.0 s to 48.5 s, against a takt of 36.8 s. The largest loss at this step is equipment downtime (uptime 84%), about 7.4 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.