SiC Dual-Sided EV Traction Inverter
Product family: 800V SiC Power Inverters.
Flow: Power-semiconductor supplier → Thermal Baseplate Clean → SiC Module Silver Sinter → Die-Level HV Test & Pot → Busbar & Cold-Plate Torque → High-Load Thermal Run-In → EV Axle Assembly Line
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Thermal Baseplate Clean | 49.0 s | 45 min | 94% | 98.6% | 1,125 | 1,350 (1.80 d) | 987 |
| 2. SiC Module Silver Sinter | 60.0 s | 38 min | 91% | 97.8% | 750 | 1,050 (1.40 d) | 767 |
| 3. Die-Level HV Test & Pot | 76.0 s | 65 min | 84% | 95.8% | 1,125 | 1,650 (2.20 d) | 544 |
| 4. Busbar & Cold-Plate Torque | 56.0 s | 15 min | 94% | 98.4% | 375 | 825 (1.10 d) | 862 |
| 5. High-Load Thermal Run-In | 45.0 s | 10 min | 96% | 99.1% | 188 | 600 (0.80 d) | 1,091 |
Key figures
- Takt time
- 72.0 s
- Lead time
- 8.81 d
- Value-added time
- 286 s
- Process cycle efficiency (PCE)
- 0.060%
- Rolled throughput yield (RTY)
- 90.1%
- Customer demand per day
- 750 units
- Line capacity per day
- 544 units
- Bottleneck
- Die-Level HV Test & Pot
Reading the bottleneck
The bottleneck is "Die-Level HV Test & Pot": it can process 544 units per day against a demand of 750 units, so it falls short of demand by 27.4%. Once downtime and scrap are counted, its cycle time grows from 76.0 s to 94.4 s, against a takt of 72.0 s. The largest loss at this step is equipment downtime (uptime 84%), about 14.5 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Powertrain & Driveline: Powertrain & Driveline
- Aluminum V6 Engine Block CNC Line
- 8-Speed Automatic Transmission Assembly
- Variable Geometry Turbocharger Cell
- EV Hairpin Stator & Traction Motor Line
- Integrated 3-in-1 E-Axle Drive Unit
- Aluminum Monoblock Brake Caliper Line
- Dual-Pinion Electric Power Steering
- Constant Velocity Half-Shaft & Joint
- Euro-7 Catalytic & SCR Aftertreatment
- EV High-Voltage Scroll A/C Compressor
- GDI High-Pressure Fuel Injector 350bar