8-Speed Automatic Transmission Assembly
Product family: 8AT Hydraulic Gearboxes.
Flow: Tier-2 gearset supplier → Case Machining Prep → Torque Converter Match → Valve Body Solenoid Test → Planetary Stack & Seal → Full Load Hot-Dyno → OEM Vehicle Assembly
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Case Machining Prep | 54.0 s | 45 min | 94% | 98.6% | 1,020 | 1,224 (1.80 d) | 896 |
| 2. Torque Converter Match | 67.0 s | 38 min | 91% | 97.8% | 680 | 952 (1.40 d) | 687 |
| 3. Valve Body Solenoid Test | 84.0 s | 65 min | 84% | 95.8% | 1,020 | 1,496 (2.20 d) | 492 |
| 4. Planetary Stack & Seal | 62.0 s | 15 min | 94% | 98.4% | 340 | 748 (1.10 d) | 779 |
| 5. Full Load Hot-Dyno | 49.0 s | 10 min | 96% | 99.1% | 170 | 544 (0.80 d) | 1,002 |
Key figures
- Takt time
- 79.4 s
- Lead time
- 8.81 d
- Value-added time
- 316 s
- Process cycle efficiency (PCE)
- 0.066%
- Rolled throughput yield (RTY)
- 90.1%
- Customer demand per day
- 680 units
- Line capacity per day
- 492 units
- Bottleneck
- Valve Body Solenoid Test
Reading the bottleneck
The bottleneck is "Valve Body Solenoid Test": it can process 492 units per day against a demand of 680 units, so it falls short of demand by 27.6%. Once downtime and scrap are counted, its cycle time grows from 84.0 s to 104 s, against a takt of 79.4 s. The largest loss at this step is equipment downtime (uptime 84%), about 16.0 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Powertrain & Driveline: Powertrain & Driveline
- Aluminum V6 Engine Block CNC Line
- Variable Geometry Turbocharger Cell
- EV Hairpin Stator & Traction Motor Line
- SiC Dual-Sided EV Traction Inverter
- Integrated 3-in-1 E-Axle Drive Unit
- Aluminum Monoblock Brake Caliper Line
- Dual-Pinion Electric Power Steering
- Constant Velocity Half-Shaft & Joint
- Euro-7 Catalytic & SCR Aftertreatment
- EV High-Voltage Scroll A/C Compressor
- GDI High-Pressure Fuel Injector 350bar