Aluminum V6 Engine Block CNC Line

Product family: Aluminum Cylinder Blocks.

Flow: Aluminum die-casting foundry → Block X-Ray & Trim → 5-Axis Rough Decking → Honing & Bore Plateau → Wash & Cam Bearing Press → CMM Leak & Air Gauge → Car-maker engine plants

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Aluminum V6 Engine Block CNC LineSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Aluminum die-casting foundry → Block X-Ray & Trim (87.0 s) → 5-Axis Rough Decking (108 s) → Honing & Bore Plateau (136 s) → Wash & Cam Bearing Press (100 s) → CMM Leak & Air Gauge (80.0 s) → Car-maker engine plants.SUPPLIERAluminumdie-castingfoundryI1.80 d1Block X-Ray &TrimC/T 87.0 sI1.40 d25-Axis RoughDeckingC/T 108 sI2.20 d3Honing & BorePlateauC/T 136 sI1.10 d4Wash & CamBearing PressC/T 100 sI0.80 d5CMM Leak & AirGaugeC/T 80.0 sI1.50 dCUSTOMERCar-makerengine plants420 / parts

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Block X-Ray & Trim87.0 s45 min94%98.6%630756 (1.80 d)556
2. 5-Axis Rough Decking108 s38 min91%97.8%420588 (1.40 d)426
3. Honing & Bore Plateau136 s65 min84%95.8%630924 (2.20 d)304
4. Wash & Cam Bearing Press100 s15 min94%98.4%210462 (1.10 d)483
5. CMM Leak & Air Gauge80.0 s10 min96%99.1%105336 (0.80 d)614

Key figures

Takt time
129 s
Lead time
8.81 d
Value-added time
511 s
Process cycle efficiency (PCE)
0.11%
Rolled throughput yield (RTY)
90.1%
Customer demand per day
420 parts
Line capacity per day
304 parts
Bottleneck
Honing & Bore Plateau

Reading the bottleneck

The bottleneck is "Honing & Bore Plateau": it can process 304 parts per day against a demand of 420 parts, so it falls short of demand by 27.6%. Once downtime and scrap are counted, its cycle time grows from 136 s to 169 s, against a takt of 129 s. The largest loss at this step is equipment downtime (uptime 84%), about 25.9 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.