Euro-7 Catalytic & SCR Aftertreatment
Product family: DPF & SCR Stainless Cans.
Flow: Stainless steel mill → 304SS Cone Hydroform → Vermiculite Mat & Stuff → Dual-Head Seam TIG Weld → Canning Diameter Calibration → Helium Backpressure Test → Commercial & Passenger OEMs
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. 304SS Cone Hydroform | 45.0 s | 45 min | 94% | 98.6% | 1,230 | 1,476 (1.80 d) | 1,075 |
| 2. Vermiculite Mat & Stuff | 55.0 s | 38 min | 91% | 97.8% | 820 | 1,148 (1.40 d) | 837 |
| 3. Dual-Head Seam TIG Weld | 70.0 s | 65 min | 84% | 95.8% | 1,230 | 1,804 (2.20 d) | 591 |
| 4. Canning Diameter Calibration | 51.0 s | 15 min | 94% | 98.4% | 410 | 902 (1.10 d) | 947 |
| 5. Helium Backpressure Test | 41.0 s | 10 min | 96% | 99.1% | 205 | 656 (0.80 d) | 1,197 |
Key figures
- Takt time
- 65.9 s
- Lead time
- 8.80 d
- Value-added time
- 262 s
- Process cycle efficiency (PCE)
- 0.055%
- Rolled throughput yield (RTY)
- 90.1%
- Customer demand per day
- 820 units
- Line capacity per day
- 591 units
- Bottleneck
- Dual-Head Seam TIG Weld
Reading the bottleneck
The bottleneck is "Dual-Head Seam TIG Weld": it can process 591 units per day against a demand of 820 units, so it falls short of demand by 27.9%. Once downtime and scrap are counted, its cycle time grows from 70.0 s to 87.0 s, against a takt of 65.9 s. The largest loss at this step is equipment downtime (uptime 84%), about 13.3 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Powertrain & Driveline: Powertrain & Driveline
- Aluminum V6 Engine Block CNC Line
- 8-Speed Automatic Transmission Assembly
- Variable Geometry Turbocharger Cell
- EV Hairpin Stator & Traction Motor Line
- SiC Dual-Sided EV Traction Inverter
- Integrated 3-in-1 E-Axle Drive Unit
- Aluminum Monoblock Brake Caliper Line
- Dual-Pinion Electric Power Steering
- Constant Velocity Half-Shaft & Joint
- EV High-Voltage Scroll A/C Compressor
- GDI High-Pressure Fuel Injector 350bar