Integrated 3-in-1 E-Axle Drive Unit
Product family: Motor-Inverter-Reducer Axle.
Flow: Driveline Tier-1 gear maker → Housing CNC Bore Align → Helical Gear Shaving → Motor-Reducer Marriage → Inverter HV Mate & Seal → NVH Acoustic Chamber Test → BEV Platform Plant
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Housing CNC Bore Align | 77.0 s | 45 min | 94% | 98.6% | 720 | 864 (1.80 d) | 628 |
| 2. Helical Gear Shaving | 95.0 s | 38 min | 91% | 97.8% | 480 | 672 (1.40 d) | 485 |
| 3. Motor-Reducer Marriage | 119 s | 65 min | 84% | 95.8% | 720 | 1,056 (2.20 d) | 348 |
| 4. Inverter HV Mate & Seal | 88.0 s | 15 min | 94% | 98.4% | 240 | 528 (1.10 d) | 549 |
| 5. NVH Acoustic Chamber Test | 70.0 s | 10 min | 96% | 99.1% | 120 | 384 (0.80 d) | 701 |
Key figures
- Takt time
- 113 s
- Lead time
- 8.81 d
- Value-added time
- 449 s
- Process cycle efficiency (PCE)
- 0.094%
- Rolled throughput yield (RTY)
- 90.1%
- Customer demand per day
- 480 units
- Line capacity per day
- 348 units
- Bottleneck
- Motor-Reducer Marriage
Reading the bottleneck
The bottleneck is "Motor-Reducer Marriage": it can process 348 units per day against a demand of 480 units, so it falls short of demand by 27.6%. Once downtime and scrap are counted, its cycle time grows from 119 s to 148 s, against a takt of 113 s. The largest loss at this step is equipment downtime (uptime 84%), about 22.7 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Powertrain & Driveline: Powertrain & Driveline
- Aluminum V6 Engine Block CNC Line
- 8-Speed Automatic Transmission Assembly
- Variable Geometry Turbocharger Cell
- EV Hairpin Stator & Traction Motor Line
- SiC Dual-Sided EV Traction Inverter
- Aluminum Monoblock Brake Caliper Line
- Dual-Pinion Electric Power Steering
- Constant Velocity Half-Shaft & Joint
- Euro-7 Catalytic & SCR Aftertreatment
- EV High-Voltage Scroll A/C Compressor
- GDI High-Pressure Fuel Injector 350bar