EV Hairpin Stator & Traction Motor Line

Product family: 800V PMSM Traction Motors.

Flow: Magnet & copper wire supplier → Lamination Stack Press → Copper Hairpin Form & Insert → Laser Hairpin Weld & Varnish → Magnet Rotor Press & Bal → Back-EMF Dyno Verification → EV Drivetrain Integrators

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: EV Hairpin Stator & Traction Motor LineSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Magnet & copper wire supplier → Lamination Stack Press (68.0 s) → Copper Hairpin Form & Insert (84.0 s) → Laser Hairpin Weld & Varnish (106 s) → Magnet Rotor Press & Bal (78.0 s) → Back-EMF Dyno Verification (62.0 s) → EV Drivetrain Integrators.SUPPLIERMagnet & copperwire supplierI1.80 d1Lamination StackPressC/T 68.0 sI1.40 d2Copper HairpinForm & InsertC/T 84.0 sI2.20 d3Laser HairpinWeld & VarnishC/T 106 sI1.10 d4Magnet RotorPress & BalC/T 78.0 sI0.80 d5Back-EMF DynoVerificationC/T 62.0 sI1.50 dCUSTOMEREV DrivetrainIntegrators540 / units

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Lamination Stack Press68.0 s45 min94%98.6%810972 (1.80 d)711
2. Copper Hairpin Form & Insert84.0 s38 min91%97.8%540756 (1.40 d)548
3. Laser Hairpin Weld & Varnish106 s65 min84%95.8%8101,188 (2.20 d)390
4. Magnet Rotor Press & Bal78.0 s15 min94%98.4%270594 (1.10 d)619
5. Back-EMF Dyno Verification62.0 s10 min96%99.1%135432 (0.80 d)792

Key figures

Takt time
100 s
Lead time
8.81 d
Value-added time
398 s
Process cycle efficiency (PCE)
0.084%
Rolled throughput yield (RTY)
90.1%
Customer demand per day
540 units
Line capacity per day
390 units
Bottleneck
Laser Hairpin Weld & Varnish

Reading the bottleneck

The bottleneck is "Laser Hairpin Weld & Varnish": it can process 390 units per day against a demand of 540 units, so it falls short of demand by 27.7%. Once downtime and scrap are counted, its cycle time grows from 106 s to 132 s, against a takt of 100 s. The largest loss at this step is equipment downtime (uptime 84%), about 20.2 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.