EV Extruded Aluminum Battery Enclosure
Product family: Underbody Crash Battery Trays.
Flow: Aluminum extrusion house → CNC Profile Mitre & Drill → Friction Stir Welding (FSW) → TIG Corner & Thermal Weld → He-Leak & Pressure Decay → E-Coat & Wax Cavity Seal → BEV Pack Assembly Plant
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. CNC Profile Mitre & Drill | 102 s | 75 min | 88% | 98.5% | 720 | 864 (2.40 d) | 440 |
| 2. Friction Stir Welding (FSW) | 126 s | 35 min | 90% | 97.4% | 288 | 648 (1.80 d) | 357 |
| 3. TIG Corner & Thermal Weld | 135 s | 40 min | 91% | 97.9% | 360 | 684 (1.90 d) | 341 |
| 4. He-Leak & Pressure Decay | 162 s | 18 min | 86% | 95.8% | 108 | 576 (1.60 d) | 256 |
| 5. E-Coat & Wax Cavity Seal | 108 s | 12 min | 95% | 98.9% | 54 | 288 (0.80 d) | 428 |
Key figures
- Takt time
- 150 s
- Lead time
- 10.0 d
- Value-added time
- 633 s
- Process cycle efficiency (PCE)
- 0.12%
- Rolled throughput yield (RTY)
- 89.0%
- Customer demand per day
- 360 units
- Line capacity per day
- 256 units
- Bottleneck
- He-Leak & Pressure Decay
Reading the bottleneck
The bottleneck is "He-Leak & Pressure Decay": it can process 256 units per day against a demand of 360 units, so it falls short of demand by 28.8%. Once downtime and scrap are counted, its cycle time grows from 162 s to 197 s, against a takt of 150 s. The largest loss at this step is equipment downtime (uptime 86%), about 26.4 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of BIW Stamping & Electromechanical: BIW Stamping & Electromechanical
- Automotive Electromechanical Assembly
- BIW Aluminum Door Shell & Hemming
- Boron Steel Hot-Stamped B-Pillar
- Hydroformed Sub-Frame Suspension Cradle
- Class-A Aluminum Hood Outer & Inner
- High-Pressure Rear Underbody Megacasting
- Roll-Formed Martensitic Bumper Beam
- 6-Layer Co-Extruded HDPE Fuel Tank
- Panoramic Glass Sunroof Frame Module
- Automotive Wiper Drive & Linkage Assembly
- Smart Power-Cinched Automotive Door Latch