Smart Power-Cinched Automotive Door Latch
Product family: E-Latch Side Door Locks.
Flow: POM resin & steel supplier → Fine-Blanking Steel Plates → POM Acoustic Overmolding → PCB Hall Switch Insert → Robotic Grease & Rivet → Cold -40°C Latch Force Test → Door Hardware Module OEM
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Fine-Blanking Steel Plates | 14.5 s | 75 min | 88% | 98.5% | 7,600 | 9,120 (2.40 d) | 4,708 |
| 2. POM Acoustic Overmolding | 17.9 s | 35 min | 90% | 97.4% | 3,040 | 6,840 (1.80 d) | 3,838 |
| 3. PCB Hall Switch Insert | 19.2 s | 40 min | 91% | 97.9% | 3,800 | 7,220 (1.90 d) | 3,647 |
| 4. Robotic Grease & Rivet | 23.0 s | 18 min | 86% | 95.8% | 1,140 | 6,080 (1.60 d) | 2,773 |
| 5. Cold -40°C Latch Force Test | 15.3 s | 12 min | 95% | 98.9% | 570 | 3,040 (0.80 d) | 4,679 |
Key figures
- Takt time
- 21.3 s
- Lead time
- 10.0 d
- Value-added time
- 89.9 s
- Process cycle efficiency (PCE)
- 0.011%
- Rolled throughput yield (RTY)
- 89.0%
- Customer demand per day
- 3,800 parts
- Line capacity per day
- 2,773 parts
- Bottleneck
- Robotic Grease & Rivet
Reading the bottleneck
The bottleneck is "Robotic Grease & Rivet": it can process 2,773 parts per day against a demand of 3,800 parts, so it falls short of demand by 27.0%. Once downtime and scrap are counted, its cycle time grows from 23.0 s to 27.9 s, against a takt of 21.3 s. The largest loss at this step is equipment downtime (uptime 86%), about 3.7 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of BIW Stamping & Electromechanical: BIW Stamping & Electromechanical
- Automotive Electromechanical Assembly
- BIW Aluminum Door Shell & Hemming
- Boron Steel Hot-Stamped B-Pillar
- EV Extruded Aluminum Battery Enclosure
- Hydroformed Sub-Frame Suspension Cradle
- Class-A Aluminum Hood Outer & Inner
- High-Pressure Rear Underbody Megacasting
- Roll-Formed Martensitic Bumper Beam
- 6-Layer Co-Extruded HDPE Fuel Tank
- Panoramic Glass Sunroof Frame Module
- Automotive Wiper Drive & Linkage Assembly