Roll-Formed Martensitic Bumper Beam
Product family: Ultra-High-Strength Crash Beams.
Flow: Martensitic steel strip mill → 22-Stand Roll Forming → In-Line Sweeping Bend → Laser Slot & Tow-Nut Weld → Zinc-Nickel Barrel Plating → Pendulum Drop Impact Audit → Front Module Tier-1
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. 22-Stand Roll Forming | 30.6 s | 75 min | 88% | 98.5% | 3,600 | 4,320 (2.40 d) | 2,231 |
| 2. In-Line Sweeping Bend | 37.8 s | 35 min | 90% | 97.4% | 1,440 | 3,240 (1.80 d) | 1,818 |
| 3. Laser Slot & Tow-Nut Weld | 41.0 s | 40 min | 91% | 97.9% | 1,800 | 3,420 (1.90 d) | 1,708 |
| 4. Zinc-Nickel Barrel Plating | 49.0 s | 18 min | 86% | 95.8% | 540 | 2,880 (1.60 d) | 1,301 |
| 5. Pendulum Drop Impact Audit | 32.4 s | 12 min | 95% | 98.9% | 270 | 1,440 (0.80 d) | 2,210 |
Key figures
- Takt time
- 45.0 s
- Lead time
- 10.0 d
- Value-added time
- 191 s
- Process cycle efficiency (PCE)
- 0.024%
- Rolled throughput yield (RTY)
- 89.0%
- Customer demand per day
- 1,800 parts
- Line capacity per day
- 1,301 parts
- Bottleneck
- Zinc-Nickel Barrel Plating
Reading the bottleneck
The bottleneck is "Zinc-Nickel Barrel Plating": it can process 1,301 parts per day against a demand of 1,800 parts, so it falls short of demand by 27.7%. Once downtime and scrap are counted, its cycle time grows from 49.0 s to 59.5 s, against a takt of 45.0 s. The largest loss at this step is equipment downtime (uptime 86%), about 8.0 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of BIW Stamping & Electromechanical: BIW Stamping & Electromechanical
- Automotive Electromechanical Assembly
- BIW Aluminum Door Shell & Hemming
- Boron Steel Hot-Stamped B-Pillar
- EV Extruded Aluminum Battery Enclosure
- Hydroformed Sub-Frame Suspension Cradle
- Class-A Aluminum Hood Outer & Inner
- High-Pressure Rear Underbody Megacasting
- 6-Layer Co-Extruded HDPE Fuel Tank
- Panoramic Glass Sunroof Frame Module
- Automotive Wiper Drive & Linkage Assembly
- Smart Power-Cinched Automotive Door Latch