Boron Steel Hot-Stamped B-Pillar
Product family: 1500 MPa Press-Hardened Pillars.
Flow: Press-hardening steel supplier → 930°C Roller Hearth Heat → Water-Cooled Die Quench → 5-Axis 3D Fiber Laser Trim → Shot-Blast Scale Clean → Destructive Bend & Laser Gauging → Crash Structure Body Shop
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. 930°C Roller Hearth Heat | 39.3 s | 75 min | 88% | 98.5% | 2,800 | 3,360 (2.40 d) | 1,737 |
| 2. Water-Cooled Die Quench | 49.0 s | 35 min | 90% | 97.4% | 1,120 | 2,520 (1.80 d) | 1,402 |
| 3. 5-Axis 3D Fiber Laser Trim | 52.0 s | 40 min | 91% | 97.9% | 1,400 | 2,660 (1.90 d) | 1,347 |
| 4. Shot-Blast Scale Clean | 62.0 s | 18 min | 86% | 95.8% | 420 | 2,240 (1.60 d) | 1,029 |
| 5. Destructive Bend & Laser Gauging | 42.0 s | 12 min | 95% | 98.9% | 210 | 1,120 (0.80 d) | 1,705 |
Key figures
- Takt time
- 57.9 s
- Lead time
- 10.0 d
- Value-added time
- 244 s
- Process cycle efficiency (PCE)
- 0.030%
- Rolled throughput yield (RTY)
- 89.0%
- Customer demand per day
- 1,400 parts
- Line capacity per day
- 1,029 parts
- Bottleneck
- Shot-Blast Scale Clean
Reading the bottleneck
The bottleneck is "Shot-Blast Scale Clean": it can process 1,029 parts per day against a demand of 1,400 parts, so it falls short of demand by 26.5%. Once downtime and scrap are counted, its cycle time grows from 62.0 s to 75.3 s, against a takt of 57.9 s. The largest loss at this step is equipment downtime (uptime 86%), about 10.1 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of BIW Stamping & Electromechanical: BIW Stamping & Electromechanical
- Automotive Electromechanical Assembly
- BIW Aluminum Door Shell & Hemming
- EV Extruded Aluminum Battery Enclosure
- Hydroformed Sub-Frame Suspension Cradle
- Class-A Aluminum Hood Outer & Inner
- High-Pressure Rear Underbody Megacasting
- Roll-Formed Martensitic Bumper Beam
- 6-Layer Co-Extruded HDPE Fuel Tank
- Panoramic Glass Sunroof Frame Module
- Automotive Wiper Drive & Linkage Assembly
- Smart Power-Cinched Automotive Door Latch