Hydroformed Sub-Frame Suspension Cradle

Product family: Front & Rear Sub-Frames.

Flow: High-strength steel tube supplier → Tube CNC Rotary Bending → High-Pressure Hydroform → Robotic MAG Multi-Pass → KTL Cathodic Dip E-Coat → Bushing Press & Datuming → Chassis Assembly Line

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Hydroformed Sub-Frame Suspension CradleSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. High-strength steel tube supplier → Tube CNC Rotary Bending (57.0 s) → High-Pressure Hydroform (71.0 s) → Robotic MAG Multi-Pass (76.0 s) → KTL Cathodic Dip E-Coat (91.0 s) → Bushing Press & Datuming (61.0 s) → Chassis Assembly Line.SUPPLIERHigh-strengthsteel tubesupplierI2.40 d1Tube CNC RotaryBendingC/T 57.0 sI1.80 d2High-PressureHydroformC/T 71.0 sI1.90 d3Robotic MAGMulti-PassC/T 76.0 sI1.60 d4KTL Cathodic DipE-CoatC/T 91.0 sI0.80 d5Bushing Press &DatumingC/T 61.0 sI1.50 dCUSTOMERChassisAssembly Line640 / parts

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Tube CNC Rotary Bending57.0 s75 min88%98.5%1,2801,536 (2.40 d)787
2. High-Pressure Hydroform71.0 s35 min90%97.4%5121,152 (1.80 d)634
3. Robotic MAG Multi-Pass76.0 s40 min91%97.9%6401,216 (1.90 d)605
4. KTL Cathodic Dip E-Coat91.0 s18 min86%95.8%1921,024 (1.60 d)456
5. Bushing Press & Datuming61.0 s12 min95%98.9%96512 (0.80 d)758

Key figures

Takt time
84.4 s
Lead time
10.0 d
Value-added time
356 s
Process cycle efficiency (PCE)
0.066%
Rolled throughput yield (RTY)
89.0%
Customer demand per day
640 parts
Line capacity per day
456 parts
Bottleneck
KTL Cathodic Dip E-Coat

Reading the bottleneck

The bottleneck is "KTL Cathodic Dip E-Coat": it can process 456 parts per day against a demand of 640 parts, so it falls short of demand by 28.7%. Once downtime and scrap are counted, its cycle time grows from 91.0 s to 110 s, against a takt of 84.4 s. The largest loss at this step is equipment downtime (uptime 86%), about 14.8 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.