6-Layer Co-Extruded HDPE Fuel Tank

Product family: Zero-Evaporation Hybrid Tanks.

Flow: HDPE/EVOH resin supplier → 6-Layer Parison Blow Mold → Post-Mold Cooling Jig → Rotary Valve Laser Cut → In-Tank Pump Hot-Plate Weld → Helium Sniff & Vacuum Test → Hybrid Vehicle General Line

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: 6-Layer Co-Extruded HDPE Fuel TankSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. HDPE/EVOH resin supplier → 6-Layer Parison Blow Mold (52.0 s) → Post-Mold Cooling Jig (65.0 s) → Rotary Valve Laser Cut (69.0 s) → In-Tank Pump Hot-Plate Weld (83.0 s) → Helium Sniff & Vacuum Test (56.0 s) → Hybrid Vehicle General Line.SUPPLIERHDPE/EVOH resinsupplierI2.40 d16-Layer ParisonBlow MoldC/T 52.0 sI1.80 d2Post-Mold CoolingJigC/T 65.0 sI1.90 d3Rotary ValveLaser CutC/T 69.0 sI1.60 d4In-Tank PumpHot-Plate WeldC/T 83.0 sI0.80 d5Helium Sniff &Vacuum TestC/T 56.0 sI1.50 dCUSTOMERHybrid VehicleGeneral Line1,050 / units

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. 6-Layer Parison Blow Mold52.0 s75 min88%98.5%2,1002,520 (2.40 d)1,313
2. Post-Mold Cooling Jig65.0 s35 min90%97.4%8401,890 (1.80 d)1,057
3. Rotary Valve Laser Cut69.0 s40 min91%97.9%1,0501,995 (1.90 d)1,015
4. In-Tank Pump Hot-Plate Weld83.0 s18 min86%95.8%3151,680 (1.60 d)768
5. Helium Sniff & Vacuum Test56.0 s12 min95%98.9%158840 (0.80 d)1,279

Key figures

Takt time
77.1 s
Lead time
10.0 d
Value-added time
325 s
Process cycle efficiency (PCE)
0.040%
Rolled throughput yield (RTY)
89.0%
Customer demand per day
1,050 units
Line capacity per day
768 units
Bottleneck
In-Tank Pump Hot-Plate Weld

Reading the bottleneck

The bottleneck is "In-Tank Pump Hot-Plate Weld": it can process 768 units per day against a demand of 1,050 units, so it falls short of demand by 26.8%. Once downtime and scrap are counted, its cycle time grows from 83.0 s to 101 s, against a takt of 77.1 s. The largest loss at this step is equipment downtime (uptime 86%), about 13.5 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.