99.8% Isostatic Technical Alumina Ceramics
Product family: Extreme-Temp Wear Components.
Flow: Calcined Alumina Producer → Spray Dry & Cold Isostatic Press → Green Diamond Lathe Turn → 1750°C Gas Sinter Shrinkage → Diamond Surface Grind → Ultrasonic Pinhole & CMM → Semicon & Metallurgy OEMs
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Spray Dry & Cold Isostatic Press | 77.0 s | 20 min | 96% | 99.1% | 720 | 768 (1.60 d) | 657 |
| 2. Green Diamond Lathe Turn | 97.0 s | 40 min | 95% | 97.6% | 720 | 672 (1.40 d) | 501 |
| 3. 1750°C Gas Sinter Shrinkage | 120 s | 45 min | 84% | 94.8% | 480 | 1,056 (2.20 d) | 340 |
| 4. Diamond Surface Grind | 88.0 s | 20 min | 92% | 97.8% | 288 | 624 (1.30 d) | 532 |
| 5. Ultrasonic Pinhole & CMM | 68.0 s | 10 min | 97% | 99.2% | 240 | 528 (1.10 d) | 747 |
Key figures
- Takt time
- 113 s
- Lead time
- 9.61 d
- Value-added time
- 450 s
- Process cycle efficiency (PCE)
- 0.087%
- Rolled throughput yield (RTY)
- 89.0%
- Customer demand per day
- 480 parts
- Line capacity per day
- 340 parts
- Bottleneck
- 1750°C Gas Sinter Shrinkage
Reading the bottleneck
The bottleneck is "1750°C Gas Sinter Shrinkage": it can process 340 parts per day against a demand of 480 parts, so it falls short of demand by 29.1%. Once downtime and scrap are counted, its cycle time grows from 120 s to 151 s, against a takt of 113 s. The largest loss at this step is equipment downtime (uptime 84%), about 22.9 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Glass, Ceramics & Mineral Wool: Glass, Ceramics & Mineral Wool
- 700-Ton/Day Tin-Bath Architectural Float Glass
- Low-E Solar-Control Tempered Facade Glass
- 120x240cm Large-Format Porcelain Slab Press
- High-Pressure Cast Vitreous China Toilet Bowl
- Borosilicate 5.1 Neutral Pharma Glass Tube Draw
- Recycled-Glass Fiberglass Insulation Batt Line
- Triple-Glazed Argon-Filled Warm-Edge IGU Unit
- 2.0mm Patterned Anti-Reflective Solar PV Glass
- Lead-Free Titanium Crystal Stemware Blowing
- 1550°C Basalt Rockwool Fire-Barrier Slab Line
- IS 10-Section Amber Beer/Pharma Glass Container