IS 10-Section Amber Beer/Pharma Glass Container

Product family: Lightweight NNPB Glass Jars.

Flow: 75% Post-Consumer Amber → Gob Weight Servo Feed Shear → 10-Section NNPB Double-Gob → Tin Hot-End & Annealing Lehr → Multi-Camera Vision Check & Squeeze → Auto Tier Pad Bulk Palletizer → Breweries & Food Jars

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: IS 10-Section Amber Beer/Pharma Glass ContainerSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. 75% Post-Consumer Amber → Gob Weight Servo Feed Shear (1.2 s) → 10-Section NNPB Double-Gob (1.2 s) → Tin Hot-End & Annealing Lehr (1.2 s) → Multi-Camera Vision Check & Squeeze (1.2 s) → Auto Tier Pad Bulk Palletizer (1.2 s) → Breweries & Food Jars.SUPPLIER75%Post-ConsumerAmberI1.60 d1Gob Weight ServoFeed ShearC/T 1.2 sI1.40 d210-Section NNPBDouble-GobC/T 1.2 sI2.20 d3Tin Hot-End &Annealing LehrC/T 1.2 sI1.30 d4Multi-CameraVision Check &…C/T 1.2 sI1.10 d5Auto Tier PadBulk PalletizerC/T 1.2 sI2.00 dCUSTOMERBreweries &Food Jars180,000 / units

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Gob Weight Servo Feed Shear1.2 s20 min96%99.1%270,000288,000 (1.60 d)63,583
2. 10-Section NNPB Double-Gob1.2 s40 min95%97.6%270,000252,000 (1.40 d)61,350
3. Tin Hot-End & Annealing Lehr1.2 s45 min84%94.8%180,000396,000 (2.20 d)51,960
4. Multi-Camera Vision Check & Squeeze1.2 s20 min92%97.8%108,000234,000 (1.30 d)59,234
5. Auto Tier Pad Bulk Palletizer1.2 s10 min97%99.2%90,000198,000 (1.10 d)63,989

Key figures

Takt time
0.5 s
Lead time
9.60 d
Value-added time
6.0 s
Process cycle efficiency (PCE)
0.001%
Rolled throughput yield (RTY)
89.0%
Customer demand per day
180,000 units
Line capacity per day
51,960 units
Bottleneck
Tin Hot-End & Annealing Lehr

Reading the bottleneck

The bottleneck is "Tin Hot-End & Annealing Lehr": it can process 51,960 units per day against a demand of 180,000 units, so it falls short of demand by 71.1%. Once downtime and scrap are counted, its cycle time grows from 1.2 s to 1.5 s, against a takt of 0.5 s. The largest loss at this step is equipment downtime (uptime 84%), about 0.2 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.