Low-E Solar-Control Tempered Facade Glass

Product family: Hard-Coat Magnetron Panes.

Flow: Float Glass Producer → Water-Jet & CNC Edge Polish → Vacuum Magnetron Silver Coat → Convection Furnace 680°C Quench → Heat-Soak Nickel Sulfide Test → Laser Corner Logo & Rack Pack → Curtain Wall Facade Builders

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Low-E Solar-Control Tempered Facade GlassSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Float Glass Producer → Water-Jet & CNC Edge Polish (39.3 s) → Vacuum Magnetron Silver Coat (50.0 s) → Convection Furnace 680°C Quench (62.0 s) → Heat-Soak Nickel Sulfide Test (45.0 s) → Laser Corner Logo & Rack Pack (34.7 s) → Curtain Wall Facade Builders.SUPPLIERFloat GlassProducerI1.60 d1Water-Jet & CNCEdge PolishC/T 39.3 sI1.40 d2Vacuum MagnetronSilver CoatC/T 50.0 sI2.20 d3ConvectionFurnace 680°C…C/T 62.0 sI1.30 d4Heat-Soak NickelSulfide TestC/T 45.0 sI1.10 d5Laser Corner Logo& Rack PackC/T 34.7 sI2.00 dCUSTOMERCurtain WallFacade Builders1,400 / parts

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Water-Jet & CNC Edge Polish39.3 s20 min96%99.1%2,1002,240 (1.60 d)1,941
2. Vacuum Magnetron Silver Coat50.0 s40 min95%97.6%2,1001,960 (1.40 d)1,472
3. Convection Furnace 680°C Quench62.0 s45 min84%94.8%1,4003,080 (2.20 d)1,006
4. Heat-Soak Nickel Sulfide Test45.0 s20 min92%97.8%8401,820 (1.30 d)1,580
5. Laser Corner Logo & Rack Pack34.7 s10 min97%99.2%7001,540 (1.10 d)2,213

Key figures

Takt time
57.9 s
Lead time
9.60 d
Value-added time
231 s
Process cycle efficiency (PCE)
0.030%
Rolled throughput yield (RTY)
89.0%
Customer demand per day
1,400 parts
Line capacity per day
1,006 parts
Bottleneck
Convection Furnace 680°C Quench

Reading the bottleneck

The bottleneck is "Convection Furnace 680°C Quench": it can process 1,006 parts per day against a demand of 1,400 parts, so it falls short of demand by 28.2%. Once downtime and scrap are counted, its cycle time grows from 62.0 s to 77.9 s, against a takt of 57.9 s. The largest loss at this step is equipment downtime (uptime 84%), about 11.8 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.