120x240cm Large-Format Porcelain Slab Press
Product family: Sintered Digital Inkjet Tiles.
Flow: Ukrainian Ball Clay & Feldspar → Wet Ball Mill & Spray Tower → 30,000T Continuous Compaction → 12-Bar Digital Inkjet Glaze → 1220°C Roller Hearth Kiln → Diamond Rectify & Laser Box → Commercial Flooring Chains
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Wet Ball Mill & Spray Tower | 6.5 s | 20 min | 96% | 99.1% | 12,750 | 13,600 (1.60 d) | 11,738 |
| 2. 30,000T Continuous Compaction | 8.2 s | 40 min | 95% | 97.6% | 12,750 | 11,900 (1.40 d) | 8,978 |
| 3. 12-Bar Digital Inkjet Glaze | 10.2 s | 45 min | 84% | 94.8% | 8,500 | 18,700 (2.20 d) | 6,113 |
| 4. 1220°C Roller Hearth Kiln | 7.4 s | 20 min | 92% | 97.8% | 5,100 | 11,050 (1.30 d) | 9,606 |
| 5. Diamond Rectify & Laser Box | 5.7 s | 10 min | 97% | 99.2% | 4,250 | 9,350 (1.10 d) | 13,471 |
Key figures
- Takt time
- 9.5 s
- Lead time
- 9.60 d
- Value-added time
- 38.0 s
- Process cycle efficiency (PCE)
- 0.005%
- Rolled throughput yield (RTY)
- 89.0%
- Customer demand per day
- 8,500 parts
- Line capacity per day
- 6,113 parts
- Bottleneck
- 12-Bar Digital Inkjet Glaze
Reading the bottleneck
The bottleneck is "12-Bar Digital Inkjet Glaze": it can process 6,113 parts per day against a demand of 8,500 parts, so it falls short of demand by 28.1%. Once downtime and scrap are counted, its cycle time grows from 10.2 s to 12.8 s, against a takt of 9.5 s. The largest loss at this step is equipment downtime (uptime 84%), about 1.9 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Glass, Ceramics & Mineral Wool: Glass, Ceramics & Mineral Wool
- 700-Ton/Day Tin-Bath Architectural Float Glass
- Low-E Solar-Control Tempered Facade Glass
- High-Pressure Cast Vitreous China Toilet Bowl
- Borosilicate 5.1 Neutral Pharma Glass Tube Draw
- Recycled-Glass Fiberglass Insulation Batt Line
- Triple-Glazed Argon-Filled Warm-Edge IGU Unit
- 99.8% Isostatic Technical Alumina Ceramics
- 2.0mm Patterned Anti-Reflective Solar PV Glass
- Lead-Free Titanium Crystal Stemware Blowing
- 1550°C Basalt Rockwool Fire-Barrier Slab Line
- IS 10-Section Amber Beer/Pharma Glass Container