Triple-Glazed Argon-Filled Warm-Edge IGU Unit

Product family: Passive-House Window Units.

Flow: Warm-Edge Spacer Coils → Auto Jumbo Cut & Wash Line → TPS Thermoplastic Spacer Apply → Argon Gas-Press Dual Assemble → 2-Part Silicone Edge Robot → Gas Chromatography & Rack → Window & Door Assemblers

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Triple-Glazed Argon-Filled Warm-Edge IGU UnitSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Warm-Edge Spacer Coils → Auto Jumbo Cut & Wash Line (23.0 s) → TPS Thermoplastic Spacer Apply (29.0 s) → Argon Gas-Press Dual Assemble (36.1 s) → 2-Part Silicone Edge Robot (26.3 s) → Gas Chromatography & Rack (20.3 s) → Window & Door Assemblers.SUPPLIERWarm-EdgeSpacer CoilsI1.60 d1Auto Jumbo Cut &Wash LineC/T 23.0 sI1.40 d2TPS ThermoplasticSpacer ApplyC/T 29.0 sI2.20 d3Argon Gas-PressDual AssembleC/T 36.1 sI1.30 d42-Part SiliconeEdge RobotC/T 26.3 sI1.10 d5GasChromatography &…C/T 20.3 sI2.00 dCUSTOMERWindow & DoorAssemblers1,600 / units

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Auto Jumbo Cut & Wash Line23.0 s20 min96%99.1%2,4002,560 (1.60 d)2,201
2. TPS Thermoplastic Spacer Apply29.0 s40 min95%97.6%2,4002,240 (1.40 d)1,675
3. Argon Gas-Press Dual Assemble36.1 s45 min84%94.8%1,6003,520 (2.20 d)1,132
4. 2-Part Silicone Edge Robot26.3 s20 min92%97.8%9602,080 (1.30 d)1,779
5. Gas Chromatography & Rack20.3 s10 min97%99.2%8001,760 (1.10 d)2,503

Key figures

Takt time
33.8 s
Lead time
9.60 d
Value-added time
135 s
Process cycle efficiency (PCE)
0.026%
Rolled throughput yield (RTY)
89.0%
Customer demand per day
1,600 units
Line capacity per day
1,132 units
Bottleneck
Argon Gas-Press Dual Assemble

Reading the bottleneck

The bottleneck is "Argon Gas-Press Dual Assemble": it can process 1,132 units per day against a demand of 1,600 units, so it falls short of demand by 29.3%. Once downtime and scrap are counted, its cycle time grows from 36.1 s to 45.3 s, against a takt of 33.8 s. The largest loss at this step is equipment downtime (uptime 84%), about 6.9 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.