High-Pressure Cast Vitreous China Toilet Bowl
Product family: Robotic Glaze-Spray Ceramic.
Flow: Kaolin Clay & Zircon Slurry → 40-Bar Resin Pressure Casting → Robotic Rim Sponge & Dry → Auto Glaze Spray Booth → 1240°C Shuttle/Tunnel Kiln → Vacuum Rim Flush & Box → Global Plumbing Distributors
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. 40-Bar Resin Pressure Casting | 38.7 s | 20 min | 96% | 99.1% | 1,425 | 1,520 (1.60 d) | 1,308 |
| 2. Robotic Rim Sponge & Dry | 49.0 s | 40 min | 95% | 97.6% | 1,425 | 1,330 (1.40 d) | 992 |
| 3. Auto Glaze Spray Booth | 61.0 s | 45 min | 84% | 94.8% | 950 | 2,090 (2.20 d) | 670 |
| 4. 1240°C Shuttle/Tunnel Kiln | 44.0 s | 20 min | 92% | 97.8% | 570 | 1,235 (1.30 d) | 1,063 |
| 5. Vacuum Rim Flush & Box | 34.1 s | 10 min | 97% | 99.2% | 475 | 1,045 (1.10 d) | 1,490 |
Key figures
- Takt time
- 56.8 s
- Lead time
- 9.60 d
- Value-added time
- 227 s
- Process cycle efficiency (PCE)
- 0.044%
- Rolled throughput yield (RTY)
- 89.0%
- Customer demand per day
- 950 parts
- Line capacity per day
- 670 parts
- Bottleneck
- Auto Glaze Spray Booth
Reading the bottleneck
The bottleneck is "Auto Glaze Spray Booth": it can process 670 parts per day against a demand of 950 parts, so it falls short of demand by 29.5%. Once downtime and scrap are counted, its cycle time grows from 61.0 s to 76.6 s, against a takt of 56.8 s. The largest loss at this step is equipment downtime (uptime 84%), about 11.6 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Glass, Ceramics & Mineral Wool: Glass, Ceramics & Mineral Wool
- 700-Ton/Day Tin-Bath Architectural Float Glass
- Low-E Solar-Control Tempered Facade Glass
- 120x240cm Large-Format Porcelain Slab Press
- Borosilicate 5.1 Neutral Pharma Glass Tube Draw
- Recycled-Glass Fiberglass Insulation Batt Line
- Triple-Glazed Argon-Filled Warm-Edge IGU Unit
- 99.8% Isostatic Technical Alumina Ceramics
- 2.0mm Patterned Anti-Reflective Solar PV Glass
- Lead-Free Titanium Crystal Stemware Blowing
- 1550°C Basalt Rockwool Fire-Barrier Slab Line
- IS 10-Section Amber Beer/Pharma Glass Container