Inline Emitter Precision Drip Irrigation Pipe

Product family: 16mm Compensating Ag Tube.

Flow: Regional LDPE & Silicone Supplier → Drippers Vibratory Bowl Orient → Melt Extrude & Emitter Insert → Vacuum Cool & Laser Drill → Inline Camera Flow Audit → Dual Automatic Roll Coiler → Large Agri Orchard Projects

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Inline Emitter Precision Drip Irrigation PipeSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Regional LDPE & Silicone Supplier → Drippers Vibratory Bowl Orient (12.3 s) → Melt Extrude & Emitter Insert (20.6 s) → Vacuum Cool & Laser Drill (13.9 s) → Inline Camera Flow Audit (16.2 s) → Dual Automatic Roll Coiler (11.2 s) → Large Agri Orchard Projects.SUPPLIERRegional LDPE &SiliconeSupplierI1.60 d1DrippersVibratory Bowl…C/T 12.3 sI2.20 d2Melt Extrude &Emitter InsertC/T 20.6 sI1.40 d3Vacuum Cool &Laser DrillC/T 13.9 sI1.20 d4Inline CameraFlow AuditC/T 16.2 sI0.90 d5Dual AutomaticRoll CoilerC/T 11.2 sI1.50 dCUSTOMERLarge AgriOrchard…4,200 / packs

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Drippers Vibratory Bowl Orient12.3 s20 min96%99.4%6,3006,720 (1.60 d)6,222
2. Melt Extrude & Emitter Insert20.6 s95 min82%96.5%8,4009,240 (2.20 d)3,002
3. Vacuum Cool & Laser Drill13.9 s15 min93%97.5%2,1005,880 (1.40 d)5,167
4. Inline Camera Flow Audit16.2 s20 min91%98.2%2,1005,040 (1.20 d)4,336
5. Dual Automatic Roll Coiler11.2 s10 min97%99.6%1,6803,780 (0.90 d)6,858

Key figures

Takt time
19.3 s
Lead time
8.80 d
Value-added time
74.2 s
Process cycle efficiency (PCE)
0.010%
Rolled throughput yield (RTY)
91.5%
Customer demand per day
4,200 packs
Line capacity per day
3,002 packs
Bottleneck
Melt Extrude & Emitter Insert

Reading the bottleneck

The bottleneck is "Melt Extrude & Emitter Insert": it can process 3,002 packs per day against a demand of 4,200 packs, so it falls short of demand by 28.5%. Once downtime and scrap are counted, its cycle time grows from 20.6 s to 26.0 s, against a takt of 19.3 s. The largest loss at this step is equipment downtime (uptime 82%), about 4.5 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.