Food-Grade Mono-rPET Thermoformed Meat Tray
Product family: 85% Recycled Flake-to-Tray.
Flow: Post-Consumer rPET Washed → SSP Solid-State De-Contam → Co-Extruded ABA Sheet Roll → Tilting-Platen Vacuum Form → High-Speed Stacker & Trim → In-Bag Vision Count & Case → Poultry & Ready-Meal Plants
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. SSP Solid-State De-Contam | 1.2 s | 20 min | 96% | 99.4% | 102,000 | 108,800 (1.60 d) | 63,775 |
| 2. Co-Extruded ABA Sheet Roll | 1.3 s | 95 min | 82% | 96.5% | 136,000 | 149,600 (2.20 d) | 47,569 |
| 3. Tilting-Platen Vacuum Form | 1.2 s | 15 min | 93% | 97.5% | 34,000 | 95,200 (1.40 d) | 59,846 |
| 4. High-Speed Stacker & Trim | 1.2 s | 20 min | 91% | 98.2% | 34,000 | 81,600 (1.20 d) | 58,532 |
| 5. In-Bag Vision Count & Case | 1.2 s | 10 min | 97% | 99.6% | 27,200 | 61,200 (0.90 d) | 64,005 |
Key figures
- Takt time
- 1.2 s
- Lead time
- 8.80 d
- Value-added time
- 6.1 s
- Process cycle efficiency (PCE)
- 0.001%
- Rolled throughput yield (RTY)
- 91.5%
- Customer demand per day
- 68,000 units
- Line capacity per day
- 47,569 units
- Bottleneck
- Co-Extruded ABA Sheet Roll
Reading the bottleneck
The bottleneck is "Co-Extruded ABA Sheet Roll": it can process 47,569 units per day against a demand of 68,000 units, so it falls short of demand by 30.0%. Once downtime and scrap are counted, its cycle time grows from 1.3 s to 1.6 s, against a takt of 1.2 s. The largest loss at this step is equipment downtime (uptime 82%), about 0.3 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Plastic Injection & Extrusion: Plastic Injection & Extrusion
- 250T Plastic Injection & Assembly
- 20L UN-Certified HDPE Chemical Jerrycan
- Triple-Chamber Calcium-Zinc PVC Window Profile
- 8.7m Biaxially Oriented BOPP Packaging Film
- 2000L UV-Stabilized Rotomolded Water Tank
- Inline Emitter Precision Drip Irrigation Pipe
- Carbon-Fiber PEEK Metal-Replacement Bracket
- Graphite-Enhanced EPS Thermal Insulation Block
- Pharma Medical PETG Sterile Barrier Blister Sheet
- 9-Layer EVOH Retort Spouted Stand-Up Pouch
- Home-Compostable PBAT/PLA Mulch & Bag Film