Home-Compostable PBAT/PLA Mulch & Bag Film

Product family: EN-13432 Bio-Polymer Blown.

Flow: Bio-Compound Producer → Low-Shear Moisture Control → Dual-Lip Air Ring Blown Film → Corona Treat & Water Ink Print → Star-Seal Perforated Roll Bag → Micro-Tensile & Tear Test → Supermarket Produce & Agri

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Home-Compostable PBAT/PLA Mulch & Bag FilmSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Bio-Compound Producer → Low-Shear Moisture Control (768 s) → Dual-Lip Air Ring Blown Film (1,284 s) → Corona Treat & Water Ink Print (864 s) → Star-Seal Perforated Roll Bag (1,008 s) → Micro-Tensile & Tear Test (696 s) → Supermarket Produce & Agri.SUPPLIERBio-CompoundProducerI1.60 d1Low-ShearMoisture ControlC/T 768 sI2.20 d2Dual-Lip Air RingBlown FilmC/T 1,284 sI1.40 d3Corona Treat &Water Ink PrintC/T 864 sI1.20 d4Star-SealPerforated Roll…C/T 1,008 sI0.91 d5Micro-Tensile &Tear TestC/T 696 sI1.51 dCUSTOMERSupermarketProduce & Agri45 / tonnes

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Low-Shear Moisture Control768 s20 min96%99.4%6872 (1.60 d)66
2. Dual-Lip Air Ring Blown Film1,284 s95 min82%96.5%9099 (2.20 d)32
3. Corona Treat & Water Ink Print864 s15 min93%97.5%2363 (1.40 d)55
4. Star-Seal Perforated Roll Bag1,008 s20 min91%98.2%2354 (1.20 d)46
5. Micro-Tensile & Tear Test696 s10 min97%99.6%1841 (0.91 d)73

Key figures

Takt time
1,200 s
Lead time
8.91 d
Value-added time
4,620 s
Process cycle efficiency (PCE)
0.96%
Rolled throughput yield (RTY)
91.5%
Customer demand per day
45 tonnes
Line capacity per day
32 tonnes
Bottleneck
Dual-Lip Air Ring Blown Film

Reading the bottleneck

The bottleneck is "Dual-Lip Air Ring Blown Film": it can process 32 tonnes per day against a demand of 45 tonnes, so it falls short of demand by 29.9%. Once downtime and scrap are counted, its cycle time grows from 1,284 s to 1,623 s, against a takt of 1,200 s. The largest loss at this step is equipment downtime (uptime 82%), about 282 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.