2000L UV-Stabilized Rotomolded Water Tank

Product family: One-Piece Seamless Tanks.

Flow: Regional LLDPE Powder Producer → 35-Mesh Powder Pulverize → Tri-Arm Biaxial Gas Oven → Misted Fan Cooling Fixture → Brass Bulkhead Fitting Bore → Ultrasonic Wall Thickness → Ag & Construction Wholesale

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: 2000L UV-Stabilized Rotomolded Water TankSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Regional LLDPE Powder Producer → 35-Mesh Powder Pulverize (364 s) → Tri-Arm Biaxial Gas Oven (608 s) → Misted Fan Cooling Fixture (409 s) → Brass Bulkhead Fitting Bore (477 s) → Ultrasonic Wall Thickness (330 s) → Ag & Construction Wholesale.SUPPLIERRegional LLDPEPowder ProducerI1.60 d135-Mesh PowderPulverizeC/T 364 sI2.20 d2Tri-Arm BiaxialGas OvenC/T 608 sI1.40 d3Misted FanCooling FixtureC/T 409 sI1.20 d4Brass BulkheadFitting BoreC/T 477 sI0.91 d5Ultrasonic WallThicknessC/T 330 sI1.51 dCUSTOMERAg &Construction…95 / units

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. 35-Mesh Powder Pulverize364 s20 min96%99.4%143152 (1.60 d)139
2. Tri-Arm Biaxial Gas Oven608 s95 min82%96.5%190209 (2.20 d)67
3. Misted Fan Cooling Fixture409 s15 min93%97.5%48133 (1.40 d)116
4. Brass Bulkhead Fitting Bore477 s20 min91%98.2%48114 (1.20 d)97
5. Ultrasonic Wall Thickness330 s10 min97%99.6%3886 (0.91 d)154

Key figures

Takt time
568 s
Lead time
8.85 d
Value-added time
2,188 s
Process cycle efficiency (PCE)
0.46%
Rolled throughput yield (RTY)
91.5%
Customer demand per day
95 units
Line capacity per day
67 units
Bottleneck
Tri-Arm Biaxial Gas Oven

Reading the bottleneck

The bottleneck is "Tri-Arm Biaxial Gas Oven": it can process 67 units per day against a demand of 95 units, so it falls short of demand by 29.9%. Once downtime and scrap are counted, its cycle time grows from 608 s to 768 s, against a takt of 568 s. The largest loss at this step is equipment downtime (uptime 82%), about 133 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.