Carbon-Fiber PEEK Metal-Replacement Bracket
Product family: 40% CF-PEEK 400°C Injection.
Flow: CF-PEEK Compound Producer → High-Temp 160°C Dessicant Dry → 180°C Mold Tool High-Pressure → Robotic Degating & Annealing → Coordinate Flatness Check → Ultrasonic Clean & Antistatic → Aerospace & Semicon Brackets
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. High-Temp 160°C Dessicant Dry | 53.0 s | 20 min | 96% | 99.4% | 975 | 1,040 (1.60 d) | 958 |
| 2. 180°C Mold Tool High-Pressure | 89.0 s | 95 min | 82% | 96.5% | 1,300 | 1,430 (2.20 d) | 455 |
| 3. Robotic Degating & Annealing | 60.0 s | 15 min | 93% | 97.5% | 325 | 910 (1.40 d) | 789 |
| 4. Coordinate Flatness Check | 70.0 s | 20 min | 91% | 98.2% | 325 | 780 (1.20 d) | 659 |
| 5. Ultrasonic Clean & Antistatic | 48.0 s | 10 min | 97% | 99.6% | 260 | 585 (0.90 d) | 1,057 |
Key figures
- Takt time
- 83.1 s
- Lead time
- 8.81 d
- Value-added time
- 320 s
- Process cycle efficiency (PCE)
- 0.067%
- Rolled throughput yield (RTY)
- 91.5%
- Customer demand per day
- 650 parts
- Line capacity per day
- 455 parts
- Bottleneck
- 180°C Mold Tool High-Pressure
Reading the bottleneck
The bottleneck is "180°C Mold Tool High-Pressure": it can process 455 parts per day against a demand of 650 parts, so it falls short of demand by 30.0%. Once downtime and scrap are counted, its cycle time grows from 89.0 s to 112 s, against a takt of 83.1 s. The largest loss at this step is equipment downtime (uptime 82%), about 19.5 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Plastic Injection & Extrusion: Plastic Injection & Extrusion
- 250T Plastic Injection & Assembly
- 20L UN-Certified HDPE Chemical Jerrycan
- Triple-Chamber Calcium-Zinc PVC Window Profile
- 8.7m Biaxially Oriented BOPP Packaging Film
- 2000L UV-Stabilized Rotomolded Water Tank
- Food-Grade Mono-rPET Thermoformed Meat Tray
- Inline Emitter Precision Drip Irrigation Pipe
- Graphite-Enhanced EPS Thermal Insulation Block
- Pharma Medical PETG Sterile Barrier Blister Sheet
- 9-Layer EVOH Retort Spouted Stand-Up Pouch
- Home-Compostable PBAT/PLA Mulch & Bag Film