Triple-Chamber Calcium-Zinc PVC Window Profile

Product family: Thermal-Break Extruded Frames.

Flow: Regional PVC Resin Producer → Automated Silo Dryblend → Twin-Screw Conical Extrude → Vacuum Calibration Bath → Co-Extruded TPE Gasket & Saw → Foil Lamination & Stillage → Fenestration Window Makers

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Triple-Chamber Calcium-Zinc PVC Window ProfileSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Regional PVC Resin Producer → Automated Silo Dryblend (18.5 s) → Twin-Screw Conical Extrude (31.0 s) → Vacuum Calibration Bath (20.8 s) → Co-Extruded TPE Gasket & Saw (24.3 s) → Foil Lamination & Stillage (16.8 s) → Fenestration Window Makers.SUPPLIERRegional PVCResin ProducerI1.60 d1Automated SiloDryblendC/T 18.5 sI2.20 d2Twin-ScrewConical ExtrudeC/T 31.0 sI1.40 d3VacuumCalibration BathC/T 20.8 sI1.20 d4Co-Extruded TPEGasket & SawC/T 24.3 sI0.90 d5Foil Lamination &StillageC/T 16.8 sI1.50 dCUSTOMERFenestrationWindow Makers2,800 / parts

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Automated Silo Dryblend18.5 s20 min96%99.4%4,2004,480 (1.60 d)4,137
2. Twin-Screw Conical Extrude31.0 s95 min82%96.5%5,6006,160 (2.20 d)1,995
3. Vacuum Calibration Bath20.8 s15 min93%97.5%1,4003,920 (1.40 d)3,453
4. Co-Extruded TPE Gasket & Saw24.3 s20 min91%98.2%1,4003,360 (1.20 d)2,890
5. Foil Lamination & Stillage16.8 s10 min97%99.6%1,1202,520 (0.90 d)4,572

Key figures

Takt time
28.9 s
Lead time
8.80 d
Value-added time
111 s
Process cycle efficiency (PCE)
0.016%
Rolled throughput yield (RTY)
91.5%
Customer demand per day
2,800 parts
Line capacity per day
1,995 parts
Bottleneck
Twin-Screw Conical Extrude

Reading the bottleneck

The bottleneck is "Twin-Screw Conical Extrude": it can process 1,995 parts per day against a demand of 2,800 parts, so it falls short of demand by 28.8%. Once downtime and scrap are counted, its cycle time grows from 31.0 s to 39.2 s, against a takt of 28.9 s. The largest loss at this step is equipment downtime (uptime 82%), about 6.8 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.