Pharma Medical PETG Sterile Barrier Blister Sheet

Product family: ISO-8 Cleanroom Calender Roll.

Flow: PETG resin producer → ISO-7 Dry Resin Conveying → Flat-Die Polishing Calender → Beta-Ray Thickness Gauge → 100% Camera Gel/Black Spec → Coreless Cleanroom Shrink Roll → MedTech Orthopedic Packers

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Pharma Medical PETG Sterile Barrier Blister SheetSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. PETG resin producer → ISO-7 Dry Resin Conveying (610 s) → Flat-Die Polishing Calender (1,020 s) → Beta-Ray Thickness Gauge (686 s) → 100% Camera Gel/Black Spec (800 s) → Coreless Cleanroom Shrink Roll (553 s) → MedTech Orthopedic Packers.SUPPLIERPETG resinproducerI1.60 d1ISO-7 Dry ResinConveyingC/T 610 sI2.20 d2Flat-DiePolishing…C/T 1,020 sI1.40 d3Beta-RayThickness GaugeC/T 686 sI1.20 d4100% CameraGel/Black SpecC/T 800 sI0.91 d5CorelessCleanroom Shrink…C/T 553 sI1.51 dCUSTOMERMedTechOrthopedic…85 / batches

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. ISO-7 Dry Resin Conveying610 s20 min96%99.4%128136 (1.60 d)125
2. Flat-Die Polishing Calender1,020 s95 min82%96.5%170187 (2.20 d)61
3. Beta-Ray Thickness Gauge686 s15 min93%97.5%43119 (1.40 d)105
4. 100% Camera Gel/Black Spec800 s20 min91%98.2%43102 (1.20 d)88
5. Coreless Cleanroom Shrink Roll553 s10 min97%99.6%3477 (0.91 d)139

Key figures

Takt time
953 s
Lead time
8.86 d
Value-added time
3,669 s
Process cycle efficiency (PCE)
0.51%
Rolled throughput yield (RTY)
91.5%
Customer demand per day
85 batches
Line capacity per day
61 batches
Bottleneck
Flat-Die Polishing Calender

Reading the bottleneck

The bottleneck is "Flat-Die Polishing Calender": it can process 61 batches per day against a demand of 85 batches, so it falls short of demand by 28.7%. Once downtime and scrap are counted, its cycle time grows from 1,020 s to 1,289 s, against a takt of 953 s. The largest loss at this step is equipment downtime (uptime 82%), about 224 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.