Graphite-Enhanced EPS Thermal Insulation Block

Product family: Graphite Grey Facade Boards.

Flow: Regional EPS Bead Producer → Steam Pre-Expansion & Silo → 24h Pentane Aging Silos → Vacuum Block Mold Steam → CNC Oscillating Hot-Wire Cut → Shrink Wrap & Lambda Test → ETICS Facade Builders

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Graphite-Enhanced EPS Thermal Insulation BlockSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Regional EPS Bead Producer → Steam Pre-Expansion & Silo (19.2 s) → 24h Pentane Aging Silos (32.1 s) → Vacuum Block Mold Steam (21.6 s) → CNC Oscillating Hot-Wire Cut (25.2 s) → Shrink Wrap & Lambda Test (17.4 s) → ETICS Facade Builders.SUPPLIERRegional EPSBead ProducerI1.60 d1SteamPre-Expansion &…C/T 19.2 sI2.20 d224h Pentane AgingSilosC/T 32.1 sI1.40 d3Vacuum Block MoldSteamC/T 21.6 sI1.20 d4CNC OscillatingHot-Wire CutC/T 25.2 sI0.90 d5Shrink Wrap &Lambda TestC/T 17.4 sI1.50 dCUSTOMERETICS FacadeBuilders1,800 / parts

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Steam Pre-Expansion & Silo19.2 s20 min96%99.4%2,7002,880 (1.60 d)2,644
2. 24h Pentane Aging Silos32.1 s95 min82%96.5%3,6003,960 (2.20 d)1,261
3. Vacuum Block Mold Steam21.6 s15 min93%97.5%9002,520 (1.40 d)2,191
4. CNC Oscillating Hot-Wire Cut25.2 s20 min91%98.2%9002,160 (1.20 d)1,830
5. Shrink Wrap & Lambda Test17.4 s10 min97%99.6%7201,620 (0.90 d)2,915

Key figures

Takt time
30.0 s
Lead time
8.80 d
Value-added time
116 s
Process cycle efficiency (PCE)
0.024%
Rolled throughput yield (RTY)
91.5%
Customer demand per day
1,800 parts
Line capacity per day
1,261 parts
Bottleneck
24h Pentane Aging Silos

Reading the bottleneck

The bottleneck is "24h Pentane Aging Silos": it can process 1,261 parts per day against a demand of 1,800 parts, so it falls short of demand by 29.9%. Once downtime and scrap are counted, its cycle time grows from 32.1 s to 40.6 s, against a takt of 30.0 s. The largest loss at this step is equipment downtime (uptime 82%), about 7.0 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.