Talalay Natural Latex Breathable Mattress Core

Product family: 7-Zone Ergonomic Bed Cores.

Flow: FSC Natural Hevea Latex → Whip Foaming & Aluminum Mold → Vacuum Expand & -30°C Freeze → CO2 Gel & 115°C Steam Cure → 4-Stage Wash & RF Tunnel Dry → ILD Compression 7-Zone Map → European Bedding Brands

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Talalay Natural Latex Breathable Mattress CoreSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. FSC Natural Hevea Latex → Whip Foaming & Aluminum Mold (199 s) → Vacuum Expand & -30°C Freeze (239 s) → CO2 Gel & 115°C Steam Cure (307 s) → 4-Stage Wash & RF Tunnel Dry (216 s) → ILD Compression 7-Zone Map (159 s) → European Bedding Brands.SUPPLIERFSC NaturalHevea LatexI1.80 d1Whip Foaming &Aluminum MoldC/T 199 sI1.60 d2Vacuum Expand &-30°C FreezeC/T 239 sI2.10 d3CO2 Gel & 115°CSteam CureC/T 307 sI1.10 d44-Stage Wash & RFTunnel DryC/T 216 sI0.90 d5ILD Compression7-Zone MapC/T 159 sI1.80 dCUSTOMEREuropeanBedding Brands190 / units

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Whip Foaming & Aluminum Mold199 s35 min94%98.4%285342 (1.80 d)244
2. Vacuum Expand & -30°C Freeze239 s30 min91%97.6%152304 (1.60 d)192
3. CO2 Gel & 115°C Steam Cure307 s40 min84%95.8%190399 (2.10 d)135
4. 4-Stage Wash & RF Tunnel Dry216 s15 min93%98.0%76209 (1.10 d)218
5. ILD Compression 7-Zone Map159 s8 min97%99.4%57171 (0.90 d)318

Key figures

Takt time
284 s
Lead time
9.32 d
Value-added time
1,120 s
Process cycle efficiency (PCE)
0.22%
Rolled throughput yield (RTY)
89.6%
Customer demand per day
190 units
Line capacity per day
135 units
Bottleneck
CO2 Gel & 115°C Steam Cure

Reading the bottleneck

The bottleneck is "CO2 Gel & 115°C Steam Cure": it can process 135 units per day against a demand of 190 units, so it falls short of demand by 28.8%. Once downtime and scrap are counted, its cycle time grows from 307 s to 381 s, against a takt of 284 s. The largest loss at this step is equipment downtime (uptime 84%), about 58.5 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.

Other scenarios in this family

More scenarios of Tires, Elastomers & Technical Rubber: Tires, Elastomers & Technical Rubber