Braided Steel Reinforced High-Pressure Hose Line

Product family: SAE 100R2 Mandrel Hydraulic.

Flow: NBR Inner Tube & Brass Wire → Nylon Mandrel Inner Tube Ext → 24-Spindle High-Speed Wire Braid → Pin-Pricked CR Outer Jacket → Lead/Autoclave Steam Cure → Water Impulse & Mandrel Eject → Hydraulic Crimping Plants

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Braided Steel Reinforced High-Pressure Hose LineSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. NBR Inner Tube & Brass Wire → Nylon Mandrel Inner Tube Ext (1,350 s) → 24-Spindle High-Speed Wire Braid (1,620 s) → Pin-Pricked CR Outer Jacket (2,083 s) → Lead/Autoclave Steam Cure (1,466 s) → Water Impulse & Mandrel Eject (1,080 s) → Hydraulic Crimping Plants.SUPPLIERNBR Inner Tube& Brass WireI1.81 d1Nylon MandrelInner Tube ExtC/T 1,350 sI1.60 d224-SpindleHigh-Speed Wire…C/T 1,620 sI2.10 d3Pin-Pricked CROuter JacketC/T 2,083 sI1.10 d4Lead/AutoclaveSteam CureC/T 1,466 sI0.90 d5Water Impulse &Mandrel EjectC/T 1,080 sI1.81 dCUSTOMERHydraulicCrimping Plants42 / batches

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Nylon Mandrel Inner Tube Ext1,350 s35 min94%98.4%6376 (1.81 d)55
2. 24-Spindle High-Speed Wire Braid1,620 s30 min91%97.6%3467 (1.60 d)43
3. Pin-Pricked CR Outer Jacket2,083 s40 min84%95.8%4288 (2.10 d)30
4. Lead/Autoclave Steam Cure1,466 s15 min93%98.0%1746 (1.10 d)49
5. Water Impulse & Mandrel Eject1,080 s8 min97%99.4%1338 (0.90 d)71

Key figures

Takt time
1,929 s
Lead time
9.40 d
Value-added time
7,599 s
Process cycle efficiency (PCE)
1.00%
Rolled throughput yield (RTY)
89.6%
Customer demand per day
42 batches
Line capacity per day
30 batches
Bottleneck
Pin-Pricked CR Outer Jacket

Reading the bottleneck

The bottleneck is "Pin-Pricked CR Outer Jacket": it can process 30 batches per day against a demand of 42 batches, so it falls short of demand by 27.7%. Once downtime and scrap are counted, its cycle time grows from 2,083 s to 2,588 s, against a takt of 1,929 s. The largest loss at this step is equipment downtime (uptime 84%), about 397 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.