3-Compound Press-On Solid Cushion Forklift Tire

Product family: Non-Marking Warehouse Tires.

Flow: High-Tear Silica NR Mix → Rim Blast & Adhesive Bonding → 3-Layer Tread Extrude Wrap → Heavy Hydraulic Daylight Cure → Sidewall Flash Lathe Trim → Hardness & Band Shear Test → Warehouse Fleet OEMs

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: 3-Compound Press-On Solid Cushion Forklift TireSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. High-Tear Silica NR Mix → Rim Blast & Adhesive Bonding (99.0 s) → 3-Layer Tread Extrude Wrap (119 s) → Heavy Hydraulic Daylight Cure (153 s) → Sidewall Flash Lathe Trim (108 s) → Hardness & Band Shear Test (80.0 s) → Warehouse Fleet OEMs.SUPPLIERHigh-TearSilica NR MixI1.80 d1Rim Blast &Adhesive BondingC/T 99.0 sI1.60 d23-Layer TreadExtrude WrapC/T 119 sI2.10 d3Heavy HydraulicDaylight CureC/T 153 sI1.10 d4Sidewall FlashLathe TrimC/T 108 sI0.90 d5Hardness & BandShear TestC/T 80.0 sI1.80 dCUSTOMERWarehouse FleetOEMs380 / units

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Rim Blast & Adhesive Bonding99.0 s35 min94%98.4%570684 (1.80 d)491
2. 3-Layer Tread Extrude Wrap119 s30 min91%97.6%304608 (1.60 d)386
3. Heavy Hydraulic Daylight Cure153 s40 min84%95.8%380798 (2.10 d)271
4. Sidewall Flash Lathe Trim108 s15 min93%98.0%152418 (1.10 d)437
5. Hardness & Band Shear Test80.0 s8 min97%99.4%114342 (0.90 d)632

Key figures

Takt time
142 s
Lead time
9.31 d
Value-added time
559 s
Process cycle efficiency (PCE)
0.11%
Rolled throughput yield (RTY)
89.6%
Customer demand per day
380 units
Line capacity per day
271 units
Bottleneck
Heavy Hydraulic Daylight Cure

Reading the bottleneck

The bottleneck is "Heavy Hydraulic Daylight Cure": it can process 271 units per day against a demand of 380 units, so it falls short of demand by 28.6%. Once downtime and scrap are counted, its cycle time grows from 153 s to 190 s, against a takt of 142 s. The largest loss at this step is equipment downtime (uptime 84%), about 29.1 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.

Other scenarios in this family

More scenarios of Tires, Elastomers & Technical Rubber: Tires, Elastomers & Technical Rubber