Graphite-Coated Precision Extruded Wiper Strip
Product family: Twin-Cut Natural Rubber Blades.
Flow: Chlorinated Natural Rubber → Dual-Tip Die Twin Extrusion → Salt-Bath Continuous Vulcanize → Halogen Chlorine & Graphite Dip → Micro-Razor Center Split Cut → Dry Wipe Friction Coefficient → Automotive Wiper Lines
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Dual-Tip Die Twin Extrusion | 2.4 s | 35 min | 94% | 98.4% | 36,000 | 43,200 (1.80 d) | 30,678 |
| 2. Salt-Bath Continuous Vulcanize | 2.8 s | 30 min | 91% | 97.6% | 19,200 | 38,400 (1.60 d) | 24,980 |
| 3. Halogen Chlorine & Graphite Dip | 3.6 s | 40 min | 84% | 95.8% | 24,000 | 50,400 (2.10 d) | 17,570 |
| 4. Micro-Razor Center Split Cut | 2.6 s | 15 min | 93% | 98.0% | 9,600 | 26,400 (1.10 d) | 27,605 |
| 5. Dry Wipe Friction Coefficient | 1.9 s | 8 min | 97% | 99.4% | 7,200 | 21,600 (0.90 d) | 40,293 |
Key figures
- Takt time
- 3.4 s
- Lead time
- 9.30 d
- Value-added time
- 13.3 s
- Process cycle efficiency (PCE)
- 0.002%
- Rolled throughput yield (RTY)
- 89.6%
- Customer demand per day
- 24,000 parts
- Line capacity per day
- 17,570 parts
- Bottleneck
- Halogen Chlorine & Graphite Dip
Reading the bottleneck
The bottleneck is "Halogen Chlorine & Graphite Dip": it can process 17,570 parts per day against a demand of 24,000 parts, so it falls short of demand by 26.8%. Once downtime and scrap are counted, its cycle time grows from 3.6 s to 4.5 s, against a takt of 3.4 s. The largest loss at this step is equipment downtime (uptime 84%), about 0.7 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Tires, Elastomers & Technical Rubber: Tires, Elastomers & Technical Rubber
- Silica-Compounded UHP Passenger Radial Tire
- Micro-Wave Co-Extruded EPDM Car Door Weatherstrip
- Cryo-Deflashed FKM Aerospace O-Rings
- Dual-Former Cleanroom Powder-Free Nitrile Glove
- Steel-Cord ST-4500 Heavy Mining Conveyor Belt
- Hydro-Elastic Aluminum/Rubber Engine Mount
- Raw-Edge Cogged Aramid Automotive Serpentine Belt
- 3-Compound Press-On Solid Cushion Forklift Tire
- Aramid-Reinforced Twin-Sphere Pipe Bellows
- Talalay Natural Latex Breathable Mattress Core
- Braided Steel Reinforced High-Pressure Hose Line