Steel-Cord ST-4500 Heavy Mining Conveyor Belt

Product family: Fire-Resistant Aramid/Steel Belt.

Flow: Brass Steel Cord Supplier → 120-Cord Tension Creel Comb → Top/Bottom Skim Calender → 20m Hydraulic Step-Cure Press → Edge Trim & Splice Prep Kit → DIN-K Fire & Adhesion Audit → Open-Pit Copper & Coal Mines

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Steel-Cord ST-4500 Heavy Mining Conveyor BeltSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Brass Steel Cord Supplier → 120-Cord Tension Creel Comb (3,150 s) → Top/Bottom Skim Calender (3,780 s) → 20m Hydraulic Step-Cure Press (4,860 s) → Edge Trim & Splice Prep Kit (3,420 s) → DIN-K Fire & Adhesion Audit (2,520 s) → Open-Pit Copper & Coal Mines.SUPPLIERBrass SteelCord SupplierI1.78 d1120-Cord TensionCreel CombC/T 3,150 sI1.61 d2Top/Bottom SkimCalenderC/T 3,780 sI2.11 d320m HydraulicStep-Cure PressC/T 4,860 sI1.11 d4Edge Trim &Splice Prep KitC/T 3,420 sI0.89 d5DIN-K Fire &Adhesion AuditC/T 2,520 sI1.78 dCUSTOMEROpen-Pit Copper& Coal Mines18 / batches

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. 120-Cord Tension Creel Comb3,150 s35 min94%98.4%2732 (1.78 d)23
2. Top/Bottom Skim Calender3,780 s30 min91%97.6%1429 (1.61 d)18
3. 20m Hydraulic Step-Cure Press4,860 s40 min84%95.8%1838 (2.11 d)13
4. Edge Trim & Splice Prep Kit3,420 s15 min93%98.0%720 (1.11 d)21
5. DIN-K Fire & Adhesion Audit2,520 s8 min97%99.4%516 (0.89 d)30

Key figures

Takt time
4,500 s
Lead time
9.50 d
Value-added time
17,730 s
Process cycle efficiency (PCE)
2.3%
Rolled throughput yield (RTY)
89.6%
Customer demand per day
18 batches
Line capacity per day
13 batches
Bottleneck
20m Hydraulic Step-Cure Press

Reading the bottleneck

The bottleneck is "20m Hydraulic Step-Cure Press": it can process 13 batches per day against a demand of 18 batches, so it falls short of demand by 27.7%. Once downtime and scrap are counted, its cycle time grows from 4,860 s to 6,039 s, against a takt of 4,500 s. The largest loss at this step is equipment downtime (uptime 84%), about 926 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.