Raw-Edge Cogged Aramid Automotive Serpentine Belt

Product family: EPDM Multi-Rib PK Belts.

Flow: Aramid Tension Cord Supplier → Rotating Drum Rubber Wrap → Spiral Aramid Cord Tension → Steam Autoclave Sleeve Cure → Diamond Multi-V Profile Grind → Dynamic Tension Length Sort → Engine Accessory Drives

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Raw-Edge Cogged Aramid Automotive Serpentine BeltSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Aramid Tension Cord Supplier → Rotating Drum Rubber Wrap (4.4 s) → Spiral Aramid Cord Tension (5.3 s) → Steam Autoclave Sleeve Cure (6.9 s) → Diamond Multi-V Profile Grind (4.8 s) → Dynamic Tension Length Sort (3.6 s) → Engine Accessory Drives.SUPPLIERAramid TensionCord SupplierI1.80 d1Rotating DrumRubber WrapC/T 4.4 sI1.60 d2Spiral AramidCord TensionC/T 5.3 sI2.10 d3Steam AutoclaveSleeve CureC/T 6.9 sI1.10 d4Diamond Multi-VProfile GrindC/T 4.8 sI0.90 d5Dynamic TensionLength SortC/T 3.6 sI1.80 dCUSTOMEREngineAccessory…8,500 / units

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Rotating Drum Rubber Wrap4.4 s35 min94%98.4%12,75015,300 (1.80 d)11,057
2. Spiral Aramid Cord Tension5.3 s30 min91%97.6%6,80013,600 (1.60 d)8,672
3. Steam Autoclave Sleeve Cure6.9 s40 min84%95.8%8,50017,850 (2.10 d)6,018
4. Diamond Multi-V Profile Grind4.8 s15 min93%98.0%3,4009,350 (1.10 d)9,826
5. Dynamic Tension Length Sort3.6 s8 min97%99.4%2,5507,650 (0.90 d)14,034

Key figures

Takt time
6.4 s
Lead time
9.30 d
Value-added time
25.0 s
Process cycle efficiency (PCE)
0.005%
Rolled throughput yield (RTY)
89.6%
Customer demand per day
8,500 units
Line capacity per day
6,018 units
Bottleneck
Steam Autoclave Sleeve Cure

Reading the bottleneck

The bottleneck is "Steam Autoclave Sleeve Cure": it can process 6,018 units per day against a demand of 8,500 units, so it falls short of demand by 29.2%. Once downtime and scrap are counted, its cycle time grows from 6.9 s to 8.6 s, against a takt of 6.4 s. The largest loss at this step is equipment downtime (uptime 84%), about 1.3 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.