Dual-Former Cleanroom Powder-Free Nitrile Glove
Product family: AQL 0.65 Medical Exam Gloves.
Flow: Nitrile Latex Producer → Porcelain Hand Wash & Coag → Dual Dip Nitrile Latex Oven → Chlorination & Double Rinse → Air Strip, Bead Roll & Count → AQL Pin-Hole Water Leak Pack → Hospital & Cleanroom Supply
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Porcelain Hand Wash & Coag | 1.2 s | 35 min | 94% | 98.4% | 210,000 | 252,000 (1.80 d) | 61,356 |
| 2. Dual Dip Nitrile Latex Oven | 1.2 s | 30 min | 91% | 97.6% | 112,000 | 224,000 (1.60 d) | 58,286 |
| 3. Chlorination & Double Rinse | 1.2 s | 40 min | 84% | 95.8% | 140,000 | 294,000 (2.10 d) | 52,709 |
| 4. Air Strip, Bead Roll & Count | 1.2 s | 15 min | 93% | 98.0% | 56,000 | 154,000 (1.10 d) | 59,811 |
| 5. AQL Pin-Hole Water Leak Pack | 1.2 s | 8 min | 97% | 99.4% | 42,000 | 126,000 (0.90 d) | 63,797 |
Key figures
- Takt time
- 0.6 s
- Lead time
- 9.30 d
- Value-added time
- 6.0 s
- Process cycle efficiency (PCE)
- 0.001%
- Rolled throughput yield (RTY)
- 89.6%
- Customer demand per day
- 140,000 units
- Line capacity per day
- 52,709 units
- Bottleneck
- Chlorination & Double Rinse
Reading the bottleneck
The bottleneck is "Chlorination & Double Rinse": it can process 52,709 units per day against a demand of 140,000 units, so it falls short of demand by 62.4%. Once downtime and scrap are counted, its cycle time grows from 1.2 s to 1.5 s, against a takt of 0.6 s. The largest loss at this step is equipment downtime (uptime 84%), about 0.2 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Tires, Elastomers & Technical Rubber: Tires, Elastomers & Technical Rubber
- Silica-Compounded UHP Passenger Radial Tire
- Micro-Wave Co-Extruded EPDM Car Door Weatherstrip
- Cryo-Deflashed FKM Aerospace O-Rings
- Steel-Cord ST-4500 Heavy Mining Conveyor Belt
- Hydro-Elastic Aluminum/Rubber Engine Mount
- Raw-Edge Cogged Aramid Automotive Serpentine Belt
- 3-Compound Press-On Solid Cushion Forklift Tire
- Aramid-Reinforced Twin-Sphere Pipe Bellows
- Talalay Natural Latex Breathable Mattress Core
- Braided Steel Reinforced High-Pressure Hose Line
- Graphite-Coated Precision Extruded Wiper Strip