Silica-Compounded UHP Passenger Radial Tire
Product family: 18–21" Low-Rolling-Resistance.
Flow: Synthetic SBR & Silica → Multi-Stage Intensive Silica Mix → Steel Cord Calender & Bead → 2-Stage Robotic Tire Building → Nitrogen Segmented Cure Press → X-Ray, Shearography & Bal → OEM Auto & Replacement
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Multi-Stage Intensive Silica Mix | 11.8 s | 35 min | 94% | 98.4% | 7,200 | 8,640 (1.80 d) | 6,240 |
| 2. Steel Cord Calender & Bead | 14.2 s | 30 min | 91% | 97.6% | 3,840 | 7,680 (1.60 d) | 4,926 |
| 3. 2-Stage Robotic Tire Building | 18.2 s | 40 min | 84% | 95.8% | 4,800 | 10,080 (2.10 d) | 3,475 |
| 4. Nitrogen Segmented Cure Press | 12.8 s | 15 min | 93% | 98.0% | 1,920 | 5,280 (1.10 d) | 5,607 |
| 5. X-Ray, Shearography & Bal | 9.5 s | 8 min | 97% | 99.4% | 1,440 | 4,320 (0.90 d) | 8,059 |
Key figures
- Takt time
- 16.9 s
- Lead time
- 9.30 d
- Value-added time
- 66.5 s
- Process cycle efficiency (PCE)
- 0.009%
- Rolled throughput yield (RTY)
- 89.6%
- Customer demand per day
- 4,800 units
- Line capacity per day
- 3,475 units
- Bottleneck
- 2-Stage Robotic Tire Building
Reading the bottleneck
The bottleneck is "2-Stage Robotic Tire Building": it can process 3,475 units per day against a demand of 4,800 units, so it falls short of demand by 27.6%. Once downtime and scrap are counted, its cycle time grows from 18.2 s to 22.6 s, against a takt of 16.9 s. The largest loss at this step is equipment downtime (uptime 84%), about 3.5 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Tires, Elastomers & Technical Rubber: Tires, Elastomers & Technical Rubber
- Micro-Wave Co-Extruded EPDM Car Door Weatherstrip
- Cryo-Deflashed FKM Aerospace O-Rings
- Dual-Former Cleanroom Powder-Free Nitrile Glove
- Steel-Cord ST-4500 Heavy Mining Conveyor Belt
- Hydro-Elastic Aluminum/Rubber Engine Mount
- Raw-Edge Cogged Aramid Automotive Serpentine Belt
- 3-Compound Press-On Solid Cushion Forklift Tire
- Aramid-Reinforced Twin-Sphere Pipe Bellows
- Talalay Natural Latex Breathable Mattress Core
- Braided Steel Reinforced High-Pressure Hose Line
- Graphite-Coated Precision Extruded Wiper Strip