Hydro-Elastic Aluminum/Rubber Engine Mount

Product family: Fluid-Damped NVH Mountings.

Flow: Al Die-Cast & Natural Rubber → Shot-Blast & Adhesive Coat → Transfer Injection Rubber Mold → Vacuum Glycol Fill & Swage → 100% Dynamic Stiffness Hz → 3-Axis Fatigue Audit Lot → Automotive Subframe Assembly

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Hydro-Elastic Aluminum/Rubber Engine MountSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Al Die-Cast & Natural Rubber → Shot-Blast & Adhesive Coat (15.7 s) → Transfer Injection Rubber Mold (18.9 s) → Vacuum Glycol Fill & Swage (24.3 s) → 100% Dynamic Stiffness Hz (17.1 s) → 3-Axis Fatigue Audit Lot (12.6 s) → Automotive Subframe Assembly.SUPPLIERAl Die-Cast &Natural RubberI1.80 d1Shot-Blast &Adhesive CoatC/T 15.7 sI1.60 d2TransferInjection Rubber…C/T 18.9 sI2.10 d3Vacuum GlycolFill & SwageC/T 24.3 sI1.10 d4100% DynamicStiffness HzC/T 17.1 sI0.90 d53-Axis FatigueAudit LotC/T 12.6 sI1.80 dCUSTOMERAutomotiveSubframe…2,400 / units

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Shot-Blast & Adhesive Coat15.7 s35 min94%98.4%3,6004,320 (1.80 d)3,099
2. Transfer Injection Rubber Mold18.9 s30 min91%97.6%1,9203,840 (1.60 d)2,432
3. Vacuum Glycol Fill & Swage24.3 s40 min84%95.8%2,4005,040 (2.10 d)1,709
4. 100% Dynamic Stiffness Hz17.1 s15 min93%98.0%9602,640 (1.10 d)2,758
5. 3-Axis Fatigue Audit Lot12.6 s8 min97%99.4%7202,160 (0.90 d)4,010

Key figures

Takt time
22.5 s
Lead time
9.30 d
Value-added time
88.6 s
Process cycle efficiency (PCE)
0.018%
Rolled throughput yield (RTY)
89.6%
Customer demand per day
2,400 units
Line capacity per day
1,709 units
Bottleneck
Vacuum Glycol Fill & Swage

Reading the bottleneck

The bottleneck is "Vacuum Glycol Fill & Swage": it can process 1,709 units per day against a demand of 2,400 units, so it falls short of demand by 28.8%. Once downtime and scrap are counted, its cycle time grows from 24.3 s to 30.2 s, against a takt of 22.5 s. The largest loss at this step is equipment downtime (uptime 84%), about 4.6 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.