Hydro-Elastic Aluminum/Rubber Engine Mount
Product family: Fluid-Damped NVH Mountings.
Flow: Al Die-Cast & Natural Rubber → Shot-Blast & Adhesive Coat → Transfer Injection Rubber Mold → Vacuum Glycol Fill & Swage → 100% Dynamic Stiffness Hz → 3-Axis Fatigue Audit Lot → Automotive Subframe Assembly
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Shot-Blast & Adhesive Coat | 15.7 s | 35 min | 94% | 98.4% | 3,600 | 4,320 (1.80 d) | 3,099 |
| 2. Transfer Injection Rubber Mold | 18.9 s | 30 min | 91% | 97.6% | 1,920 | 3,840 (1.60 d) | 2,432 |
| 3. Vacuum Glycol Fill & Swage | 24.3 s | 40 min | 84% | 95.8% | 2,400 | 5,040 (2.10 d) | 1,709 |
| 4. 100% Dynamic Stiffness Hz | 17.1 s | 15 min | 93% | 98.0% | 960 | 2,640 (1.10 d) | 2,758 |
| 5. 3-Axis Fatigue Audit Lot | 12.6 s | 8 min | 97% | 99.4% | 720 | 2,160 (0.90 d) | 4,010 |
Key figures
- Takt time
- 22.5 s
- Lead time
- 9.30 d
- Value-added time
- 88.6 s
- Process cycle efficiency (PCE)
- 0.018%
- Rolled throughput yield (RTY)
- 89.6%
- Customer demand per day
- 2,400 units
- Line capacity per day
- 1,709 units
- Bottleneck
- Vacuum Glycol Fill & Swage
Reading the bottleneck
The bottleneck is "Vacuum Glycol Fill & Swage": it can process 1,709 units per day against a demand of 2,400 units, so it falls short of demand by 28.8%. Once downtime and scrap are counted, its cycle time grows from 24.3 s to 30.2 s, against a takt of 22.5 s. The largest loss at this step is equipment downtime (uptime 84%), about 4.6 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Tires, Elastomers & Technical Rubber: Tires, Elastomers & Technical Rubber
- Silica-Compounded UHP Passenger Radial Tire
- Micro-Wave Co-Extruded EPDM Car Door Weatherstrip
- Cryo-Deflashed FKM Aerospace O-Rings
- Dual-Former Cleanroom Powder-Free Nitrile Glove
- Steel-Cord ST-4500 Heavy Mining Conveyor Belt
- Raw-Edge Cogged Aramid Automotive Serpentine Belt
- 3-Compound Press-On Solid Cushion Forklift Tire
- Aramid-Reinforced Twin-Sphere Pipe Bellows
- Talalay Natural Latex Breathable Mattress Core
- Braided Steel Reinforced High-Pressure Hose Line
- Graphite-Coated Precision Extruded Wiper Strip