Civil Engineering, Bridges, Tunnels & Rail VSM Scenarios
12 scenarios of Civil Engineering, Bridges, Tunnels & Rail, built on the same five steps. They differ by scale: demand, shifts, cycle times and buffers.
Shared steps
All 12 scenarios follow the same flow, from supplier to customer: Surveying & Earthwork Prep → Rebar Cage & Formwork Jig → Concrete Pour / TBM Ring Install → Cure, Post-Tension & Grind → NDT Core & Load Acceptance. What changes from one scenario to the next is the volume and the pace, so the same step can be the constraint in one scenario and not in another.
Scenario comparison
Choose the scenario closest to your daily demand and shift pattern, then adjust the figures in the editor. All values are illustrative starting points.
| Scenario | Demand | Shifts | Takt | Lead time | PCE | Bottleneck |
|---|---|---|---|---|---|---|
| Continuous GPS Asphalt Highway Paving Train | 240 tonnes per day | 2 | 225 s | 8.52 d | 0.19% | GPS 3D Millimeter Paver Lay |
| 10m Slurry TBM Metro Tunnel Advance & Ring Cycle | 12 cases per day | 3 | 6,750 s | 8.83 d | 3.7% | Erector Arm Gasketed Ring Set |
| Automated Continuous Welded High-Speed Rail Track | 180 batches per day | 2 | 300 s | 8.52 d | 0.26% | Flash-Butt Mobile Rail Weld |
| 2000-Ton Reinforced Offshore-Onshore Wind Base | 4 cases per day | 1 | 6,750 s | 9.24 d | 10.7% | 28-Ton Rebar Cage & Ducts |
| Balanced Cantilever Cast-in-Situ Bridge Span | 6 cases per day | 2 | 9,000 s | 9.32 d | 7.0% | Balanced Symmetric Concrete |
| Hydromill Concrete Diaphragm Station Wall | 8 cases per day | 2 | 6,750 s | 8.99 d | 5.5% | Ultrasonic Verticality Check |
| 6-Hour Nighttime Airport Runway Asphalt Rehab | 4 cases per day | 1 | 6,750 s | 9.24 d | 10.7% | Echelon Twin-Paver Asphalt Lay |
| GPS Machine-Guided Highway Cut-and-Fill Haul | 320 batches per day | 2 | 169 s | 8.51 d | 0.14% | Articulated Dump Truck Cycle |
| Coastal Harbor Breakwater Interlocking Armor Placement | 24 parts per day | 1 | 1,125 s | 8.62 d | 1.9% | Barge Crane Underwater Drop |
| Automated GPS Solar Tracker Steel Post Driving | 420 parts per day | 1 | 64.3 s | 8.51 d | 0.11% | Hydraulic Post Ramming |
| 1600mm Ductile Iron Potable Water Mainline Lay | 65 parts per day | 1 | 415 s | 8.57 d | 0.71% | Thrust Block & Valve Chamber |
| Urban Street Embedded Acoustic Light-Rail Track | 45 parts per day | 1 | 600 s | 8.60 d | 1.0% | Aluminothermic Joint Welding |