Coastal Harbor Breakwater Interlocking Armor Placement

Product family: GPS-Guided Marine Block Drop.

Flow: Concrete Casting Yard → Geo-Textile & Core Filter Rock → Multi-Beam Sonar Toe Trench → Barge Crane Underwater Drop → 3D Sonar Interlock Verify → Armor Crest Concrete Cap → Port Breakwater Expansion

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Coastal Harbor Breakwater Interlocking Armor PlacementSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Concrete Casting Yard → Geo-Textile & Core Filter Rock (765 s) → Multi-Beam Sonar Toe Trench (945 s) → Barge Crane Underwater Drop (1,215 s) → 3D Sonar Interlock Verify (878 s) → Armor Crest Concrete Cap (630 s) → Port Breakwater Expansion.SUPPLIERConcreteCasting YardI1.50 d1Geo-Textile &Core Filter RockC/T 765 sI1.79 d2Multi-Beam SonarToe TrenchC/T 945 sI2.21 d3Barge CraneUnderwater DropC/T 1,215 sI1.58 d43D SonarInterlock VerifyC/T 878 sI0.79 d5Armor CrestConcrete CapC/T 630 sI0.58 dCUSTOMERPort BreakwaterExpansion24 / parts

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Geo-Textile & Core Filter Rock765 s25 min94%97.6%1936 (1.50 d)30
2. Multi-Beam Sonar Toe Trench945 s30 min91%96.5%1443 (1.79 d)22
3. Barge Crane Underwater Drop1,215 s40 min84%94.8%1253 (2.21 d)15
4. 3D Sonar Interlock Verify878 s20 min93%98.0%1238 (1.58 d)26
5. Armor Crest Concrete Cap630 s10 min97%99.1%719 (0.79 d)38

Key figures

Takt time
1,125 s
Lead time
8.62 d
Value-added time
4,433 s
Process cycle efficiency (PCE)
1.9%
Rolled throughput yield (RTY)
86.7%
Customer demand per day
24 parts
Line capacity per day
15 parts
Bottleneck
Barge Crane Underwater Drop

Reading the bottleneck

The bottleneck is "Barge Crane Underwater Drop": it can process 15 parts per day against a demand of 24 parts, so it falls short of demand by 39.4%. Once downtime and scrap are counted, its cycle time grows from 1,215 s to 1,526 s, against a takt of 1,125 s. The largest loss at this step is equipment downtime (uptime 84%), about 231 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.

Other scenarios in this family

More scenarios of Civil Engineering, Bridges, Tunnels & Rail: Civil Engineering, Bridges, Tunnels & Rail