Urban Street Embedded Acoustic Light-Rail Track

Product family: Vibration-Isolated City Tram.

Flow: Polymer Track Embedding & Grooved Rail → Utility Diversion & Concrete Slab → Polymer Elastomer Channel Pour → Aluminothermic Joint Welding → Asphalt Wear Course & Paving → Bogie Clearance & Strayed Test → City Public Transit Agencies

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Urban Street Embedded Acoustic Light-Rail TrackSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Polymer Track Embedding & Grooved Rail → Utility Diversion & Concrete Slab (408 s) → Polymer Elastomer Channel Pour (504 s) → Aluminothermic Joint Welding (648 s) → Asphalt Wear Course & Paving (468 s) → Bogie Clearance & Strayed Test (336 s) → City Public Transit Agencies.SUPPLIERPolymer TrackEmbedding &Grooved RailI1.51 d1Utility Diversion& Concrete SlabC/T 408 sI1.80 d2Polymer ElastomerChannel PourC/T 504 sI2.20 d3AluminothermicJoint WeldingC/T 648 sI1.60 d4Asphalt WearCourse & PavingC/T 468 sI0.80 d5Bogie Clearance &Strayed TestC/T 336 sI0.60 dCUSTOMERCity PublicTransit…45 / parts

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Utility Diversion & Concrete Slab408 s25 min94%97.6%3668 (1.51 d)56
2. Polymer Elastomer Channel Pour504 s30 min91%96.5%2781 (1.80 d)42
3. Aluminothermic Joint Welding648 s40 min84%94.8%2399 (2.20 d)27
4. Asphalt Wear Course & Paving468 s20 min93%98.0%2372 (1.60 d)48
5. Bogie Clearance & Strayed Test336 s10 min97%99.1%1436 (0.80 d)72

Key figures

Takt time
600 s
Lead time
8.60 d
Value-added time
2,364 s
Process cycle efficiency (PCE)
1.0%
Rolled throughput yield (RTY)
86.7%
Customer demand per day
45 parts
Line capacity per day
27 parts
Bottleneck
Aluminothermic Joint Welding

Reading the bottleneck

The bottleneck is "Aluminothermic Joint Welding": it can process 27 parts per day against a demand of 45 parts, so it falls short of demand by 39.1%. Once downtime and scrap are counted, its cycle time grows from 648 s to 814 s, against a takt of 600 s. The largest loss at this step is equipment downtime (uptime 84%), about 123 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.