Continuous GPS Asphalt Highway Paving Train
Product family: SMA Polymer-Modified Lanes.
Flow: Hot-Mix Asphalt Plant Haul → Tack-Coat Emulsion Spray → Shuttle Buggy Material Transfer → GPS 3D Millimeter Paver Lay → Oscillatory + Pneumatic Rollers → Nuclear Density & IRI Smoothness → National Motorway Network
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Tack-Coat Emulsion Spray | 153 s | 25 min | 94% | 97.6% | 192 | 360 (1.50 d) | 313 |
| 2. Shuttle Buggy Material Transfer | 189 s | 30 min | 91% | 96.5% | 144 | 432 (1.80 d) | 237 |
| 3. GPS 3D Millimeter Paver Lay | 243 s | 40 min | 84% | 94.8% | 120 | 528 (2.20 d) | 161 |
| 4. Oscillatory + Pneumatic Rollers | 176 s | 20 min | 93% | 98.0% | 120 | 384 (1.60 d) | 267 |
| 5. Nuclear Density & IRI Smoothness | 126 s | 10 min | 97% | 99.1% | 72 | 192 (0.80 d) | 397 |
Key figures
- Takt time
- 225 s
- Lead time
- 8.52 d
- Value-added time
- 887 s
- Process cycle efficiency (PCE)
- 0.19%
- Rolled throughput yield (RTY)
- 86.7%
- Customer demand per day
- 240 tonnes
- Line capacity per day
- 161 tonnes
- Bottleneck
- GPS 3D Millimeter Paver Lay
Reading the bottleneck
The bottleneck is "GPS 3D Millimeter Paver Lay": it can process 161 tonnes per day against a demand of 240 tonnes, so it falls short of demand by 32.8%. Once downtime and scrap are counted, its cycle time grows from 243 s to 305 s, against a takt of 225 s. The largest loss at this step is equipment downtime (uptime 84%), about 46.3 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Civil Engineering, Bridges, Tunnels & Rail: Civil Engineering, Bridges, Tunnels & Rail
- 10m Slurry TBM Metro Tunnel Advance & Ring Cycle
- Automated Continuous Welded High-Speed Rail Track
- 2000-Ton Reinforced Offshore-Onshore Wind Base
- Balanced Cantilever Cast-in-Situ Bridge Span
- Hydromill Concrete Diaphragm Station Wall
- 6-Hour Nighttime Airport Runway Asphalt Rehab
- GPS Machine-Guided Highway Cut-and-Fill Haul
- Coastal Harbor Breakwater Interlocking Armor Placement
- Automated GPS Solar Tracker Steel Post Driving
- 1600mm Ductile Iron Potable Water Mainline Lay
- Urban Street Embedded Acoustic Light-Rail Track