Automated Continuous Welded High-Speed Rail Track
Product family: Slab & Ballast Rail Laying.
Flow: Concrete Sleepers & 60E1 Rail → Laser Graded Sub-Ballast Prep → Track-Laying Machine Sleepers → Flash-Butt Mobile Rail Weld → Ballast Tamp & Align → Ultrasonic Rail Head Test → National High-Speed Rail
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Laser Graded Sub-Ballast Prep | 204 s | 25 min | 94% | 97.6% | 144 | 270 (1.50 d) | 234 |
| 2. Track-Laying Machine Sleepers | 252 s | 30 min | 91% | 96.5% | 108 | 324 (1.80 d) | 178 |
| 3. Flash-Butt Mobile Rail Weld | 324 s | 40 min | 84% | 94.8% | 90 | 396 (2.20 d) | 121 |
| 4. Ballast Tamp & Align | 234 s | 20 min | 93% | 98.0% | 90 | 288 (1.60 d) | 201 |
| 5. Ultrasonic Rail Head Test | 168 s | 10 min | 97% | 99.1% | 54 | 144 (0.80 d) | 298 |
Key figures
- Takt time
- 300 s
- Lead time
- 8.52 d
- Value-added time
- 1,182 s
- Process cycle efficiency (PCE)
- 0.26%
- Rolled throughput yield (RTY)
- 86.7%
- Customer demand per day
- 180 batches
- Line capacity per day
- 121 batches
- Bottleneck
- Flash-Butt Mobile Rail Weld
Reading the bottleneck
The bottleneck is "Flash-Butt Mobile Rail Weld": it can process 121 batches per day against a demand of 180 batches, so it falls short of demand by 32.8%. Once downtime and scrap are counted, its cycle time grows from 324 s to 407 s, against a takt of 300 s. The largest loss at this step is equipment downtime (uptime 84%), about 61.7 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Civil Engineering, Bridges, Tunnels & Rail: Civil Engineering, Bridges, Tunnels & Rail
- Continuous GPS Asphalt Highway Paving Train
- 10m Slurry TBM Metro Tunnel Advance & Ring Cycle
- 2000-Ton Reinforced Offshore-Onshore Wind Base
- Balanced Cantilever Cast-in-Situ Bridge Span
- Hydromill Concrete Diaphragm Station Wall
- 6-Hour Nighttime Airport Runway Asphalt Rehab
- GPS Machine-Guided Highway Cut-and-Fill Haul
- Coastal Harbor Breakwater Interlocking Armor Placement
- Automated GPS Solar Tracker Steel Post Driving
- 1600mm Ductile Iron Potable Water Mainline Lay
- Urban Street Embedded Acoustic Light-Rail Track