6-Hour Nighttime Airport Runway Asphalt Rehab

Product family: 05:30 AM Zero-Delay Reopen.

Flow: 24/7 Batch Plant & Fleet → NOTAM Closure Cold Mill Plan → Rotary Sweeper & Tack Coat → Echelon Twin-Paver Asphalt Lay → Rapid Thermal Cooling & Groov → FOD Sweeper & Friction Open → International Hub Airports

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: 6-Hour Nighttime Airport Runway Asphalt RehabSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. 24/7 Batch Plant & Fleet → NOTAM Closure Cold Mill Plan (4,590 s) → Rotary Sweeper & Tack Coat (5,670 s) → Echelon Twin-Paver Asphalt Lay (7,290 s) → Rapid Thermal Cooling & Groov (5,265 s) → FOD Sweeper & Friction Open (3,780 s) → International Hub Airports.SUPPLIER24/7 BatchPlant & FleetI1.50 d1NOTAM ClosureCold Mill PlanC/T 4,590 sI1.75 d2Rotary Sweeper &Tack CoatC/T 5,670 sI2.25 d3EchelonTwin-Paver…C/T 7,290 sI1.50 d4Rapid ThermalCooling & GroovC/T 5,265 sI0.75 d5FOD Sweeper &Friction OpenC/T 3,780 sI0.50 dCUSTOMERInternationalHub Airports4 / cases

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. NOTAM Closure Cold Mill Plan4,590 s25 min94%97.6%36 (1.50 d)5
2. Rotary Sweeper & Tack Coat5,670 s30 min91%96.5%27 (1.75 d)4
3. Echelon Twin-Paver Asphalt Lay7,290 s40 min84%94.8%29 (2.25 d)2
4. Rapid Thermal Cooling & Groov5,265 s20 min93%98.0%26 (1.50 d)4
5. FOD Sweeper & Friction Open3,780 s10 min97%99.1%13 (0.75 d)7

Key figures

Takt time
6,750 s
Lead time
9.24 d
Value-added time
26,595 s
Process cycle efficiency (PCE)
10.7%
Rolled throughput yield (RTY)
86.7%
Customer demand per day
4 cases
Line capacity per day
2 cases
Bottleneck
Echelon Twin-Paver Asphalt Lay

Reading the bottleneck

The bottleneck is "Echelon Twin-Paver Asphalt Lay": it can process 2 cases per day against a demand of 4 cases, so it falls short of demand by 39.4%. Once downtime and scrap are counted, its cycle time grows from 7,290 s to 9,155 s, against a takt of 6,750 s. The largest loss at this step is equipment downtime (uptime 84%), about 1,389 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.

Other scenarios in this family

More scenarios of Civil Engineering, Bridges, Tunnels & Rail: Civil Engineering, Bridges, Tunnels & Rail