45m Precast Prestressed Concrete Bridge Girder

Product family: AASHTO I-Beam & Box Girders.

Flow: Low-Carbon Cement & Strand → Strand Tension Jacking Bed → Automated Cage & Form Close → Self-Consolidate Concrete Pour → Steam Curing & Strand Release → Cam-Check & Heavy Beam Truck → Highway DOT Bridges

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: 45m Precast Prestressed Concrete Bridge GirderSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Low-Carbon Cement & Strand → Strand Tension Jacking Bed (5,850 s) → Automated Cage & Form Close (6,480 s) → Self-Consolidate Concrete Pour (9,630 s) → Steam Curing & Strand Release (7,200 s) → Cam-Check & Heavy Beam Truck (4,860 s) → Highway DOT Bridges.SUPPLIERLow-CarbonCement & StrandI1.33 d1Strand TensionJacking BedC/T 5,850 sI1.17 d2Automated Cage &Form CloseC/T 6,480 sI2.00 d3Self-ConsolidateConcrete PourC/T 9,630 sI1.00 d4Steam Curing &Strand ReleaseC/T 7,200 sI0.67 d5Cam-Check & HeavyBeam TruckC/T 4,860 sI0.83 dCUSTOMERHighway DOTBridges6 / parts

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Strand Tension Jacking Bed5,850 s35 min93%98.2%58 (1.33 d)8
2. Automated Cage & Form Close6,480 s20 min94%97.6%37 (1.17 d)7
3. Self-Consolidate Concrete Pour9,630 s30 min86%93.0%212 (2.00 d)4
4. Steam Curing & Strand Release7,200 s15 min94%97.2%26 (1.00 d)7
5. Cam-Check & Heavy Beam Truck4,860 s10 min97%99.1%24 (0.67 d)10

Key figures

Takt time
9,000 s
Lead time
7.63 d
Value-added time
34,020 s
Process cycle efficiency (PCE)
8.3%
Rolled throughput yield (RTY)
85.9%
Customer demand per day
6 parts
Line capacity per day
4 parts
Bottleneck
Self-Consolidate Concrete Pour

Reading the bottleneck

The bottleneck is "Self-Consolidate Concrete Pour": it can process 4 parts per day against a demand of 6 parts, so it falls short of demand by 32.7%. Once downtime and scrap are counted, its cycle time grows from 9,630 s to 12,041 s, against a takt of 9,000 s. The largest loss at this step is equipment downtime (uptime 86%), about 1,568 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.