Carousel Automated Hollowcore & Sandwich Wall

Product family: Insulated Architectural Concrete.

Flow: White Cement & EPS Insulation → Laser Plot & Magnet Shutter → First Wythe & Insulation Lay → Truss Anchor & Second Pour → Heated Cure Chamber 12-Hr → Vertical Tilt-Frame Polish → Industrial Warehouses

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Carousel Automated Hollowcore & Sandwich WallSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. White Cement & EPS Insulation → Laser Plot & Magnet Shutter (836 s) → First Wythe & Insulation Lay (926 s) → Truss Anchor & Second Pour (1,376 s) → Heated Cure Chamber 12-Hr (1,029 s) → Vertical Tilt-Frame Polish (694 s) → Industrial Warehouses.SUPPLIERWhite Cement &EPS InsulationI1.40 d1Laser Plot &Magnet ShutterC/T 836 sI1.19 d2First Wythe &Insulation LayC/T 926 sI2.00 d3Truss Anchor &Second PourC/T 1,376 sI1.00 d4Heated CureChamber 12-HrC/T 1,029 sI0.60 d5VerticalTilt-Frame PolishC/T 694 sI0.81 dCUSTOMERIndustrialWarehouses42 / parts

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Laser Plot & Magnet Shutter836 s35 min93%98.2%3459 (1.40 d)56
2. First Wythe & Insulation Lay926 s20 min94%97.6%2150 (1.19 d)51
3. Truss Anchor & Second Pour1,376 s30 min86%93.0%1784 (2.00 d)29
4. Heated Cure Chamber 12-Hr1,029 s15 min94%97.2%1342 (1.00 d)45
5. Vertical Tilt-Frame Polish694 s10 min97%99.1%1125 (0.60 d)72

Key figures

Takt time
1,286 s
Lead time
7.09 d
Value-added time
4,861 s
Process cycle efficiency (PCE)
1.3%
Rolled throughput yield (RTY)
85.9%
Customer demand per day
42 parts
Line capacity per day
29 parts
Bottleneck
Truss Anchor & Second Pour

Reading the bottleneck

The bottleneck is "Truss Anchor & Second Pour": it can process 29 parts per day against a demand of 42 parts, so it falls short of demand by 31.4%. Once downtime and scrap are counted, its cycle time grows from 1,376 s to 1,720 s, against a takt of 1,286 s. The largest loss at this step is equipment downtime (uptime 86%), about 224 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.