Turnkey BSL-3 / GMP Modular Cleanroom Pod
Product family: Pre-Commissioned Pharma Suites.
Flow: HEPA Filter & HPL Walls → Steel Chassis & Airlock Weld → Flush GMP Wall & Cove Vinyl → HEPA Ceiling & DDC Controls → Smoke Pattern & Particle Test → Air-Tight Ship Wrap to Site → Biotech & Cell Therapy Fabs
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Steel Chassis & Airlock Weld | 4,388 s | 35 min | 93% | 98.2% | 3 | 6 (1.50 d) | 5 |
| 2. Flush GMP Wall & Cove Vinyl | 4,860 s | 20 min | 94% | 97.6% | 2 | 5 (1.25 d) | 5 |
| 3. HEPA Ceiling & DDC Controls | 7,223 s | 30 min | 86% | 93.0% | 2 | 8 (2.00 d) | 3 |
| 4. Smoke Pattern & Particle Test | 5,400 s | 15 min | 94% | 97.2% | 1 | 4 (1.00 d) | 4 |
| 5. Air-Tight Ship Wrap to Site | 3,645 s | 10 min | 97% | 99.1% | 1 | 2 (0.50 d) | 7 |
Key figures
- Takt time
- 6,750 s
- Lead time
- 7.95 d
- Value-added time
- 25,516 s
- Process cycle efficiency (PCE)
- 11.9%
- Rolled throughput yield (RTY)
- 85.9%
- Customer demand per day
- 4 modules
- Line capacity per day
- 3 modules
- Bottleneck
- HEPA Ceiling & DDC Controls
Reading the bottleneck
The bottleneck is "HEPA Ceiling & DDC Controls": it can process 3 modules per day against a demand of 4 modules, so it falls short of demand by 35.2%. Once downtime and scrap are counted, its cycle time grows from 7,223 s to 9,031 s, against a takt of 6,750 s. The largest loss at this step is equipment downtime (uptime 86%), about 1,176 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Modular Construction & Offsite Prefab: Modular Construction & Offsite Prefab
- Offsite Prefab Building Modules
- Offsite Prefabricated Tiled Bathroom Wet-Pod
- Automated Gang-Nail Timber Roof Truss Line
- Unitized Curtain-Wall Aluminum-Glass Facade
- Multi-Service Prefab Corridor & Riser Rack
- 45m Precast Prestressed Concrete Bridge Girder
- Carousel Automated Hollowcore & Sandwich Wall
- 80m Clear-Span Roof Structural Steel Truss
- Commercial Prefab Containerized Kitchen Pod
- Expandable Solar-Powered Mobile Clinic Unit
- Custom Acoustic Architectural Precast Stair Flight