80m Clear-Span Roof Structural Steel Truss

Product family: Shot-Blasted Welded Trusses.

Flow: Structural Steel Sections (HEB/IPE) → CNC Beam Drill & Cope Line → Shop Jig Fit-Up & Tack Weld → MAG Structural & UT Inspect → SA2.5 Blast & Intumescent Paint → Sequence Bundle Site Deliver → Logistics Warehouses & Hangars

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: 80m Clear-Span Roof Structural Steel TrussSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Structural Steel Sections (HEB/IPE) → CNC Beam Drill & Cope Line (2,925 s) → Shop Jig Fit-Up & Tack Weld (3,240 s) → MAG Structural & UT Inspect (4,815 s) → SA2.5 Blast & Intumescent Paint (3,600 s) → Sequence Bundle Site Deliver (2,430 s) → Logistics Warehouses & Hangars.SUPPLIERStructuralSteel Sections(HEB/IPE)I1.42 d1CNC Beam Drill &Cope LineC/T 2,925 sI1.17 d2Shop Jig Fit-Up &Tack WeldC/T 3,240 sI2.00 d3MAG Structural &UT InspectC/T 4,815 sI1.00 d4SA2.5 Blast &Intumescent PaintC/T 3,600 sI0.58 d5Sequence BundleSite DeliverC/T 2,430 sI0.83 dCUSTOMERLogisticsWarehouses &…12 / assemblies

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. CNC Beam Drill & Cope Line2,925 s35 min93%98.2%1017 (1.42 d)16
2. Shop Jig Fit-Up & Tack Weld3,240 s20 min94%97.6%614 (1.17 d)15
3. MAG Structural & UT Inspect4,815 s30 min86%93.0%524 (2.00 d)8
4. SA2.5 Blast & Intumescent Paint3,600 s15 min94%97.2%412 (1.00 d)13
5. Sequence Bundle Site Deliver2,430 s10 min97%99.1%37 (0.58 d)20

Key figures

Takt time
4,500 s
Lead time
7.32 d
Value-added time
17,010 s
Process cycle efficiency (PCE)
4.3%
Rolled throughput yield (RTY)
85.9%
Customer demand per day
12 assemblies
Line capacity per day
8 assemblies
Bottleneck
MAG Structural & UT Inspect

Reading the bottleneck

The bottleneck is "MAG Structural & UT Inspect": it can process 8 assemblies per day against a demand of 12 assemblies, so it falls short of demand by 31.2%. Once downtime and scrap are counted, its cycle time grows from 4,815 s to 6,020 s, against a takt of 4,500 s. The largest loss at this step is equipment downtime (uptime 86%), about 784 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.