Commercial Prefab Containerized Kitchen Pod

Product family: Stainless Turnkey Ghost Kitchens.

Flow: Commercial Ranges & Stainless → Insulated Steel Box Weld → FRP Washable Wall & Quarry Tile → Gas, Grease Trap & Suppression Pipe → Stainless Appliances Lock-Down → Gas Engineer & Electrical PAT Cert → Universities & Event Venues

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Commercial Prefab Containerized Kitchen PodSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Commercial Ranges & Stainless → Insulated Steel Box Weld (2,925 s) → FRP Washable Wall & Quarry Tile (3,240 s) → Gas, Grease Trap & Suppression Pipe (4,815 s) → Stainless Appliances Lock-Down (3,600 s) → Gas Engineer & Electrical PAT Cert (2,430 s) → Universities & Event Venues.SUPPLIERCommercialRanges &StainlessI1.33 d1Insulated SteelBox WeldC/T 2,925 sI1.17 d2FRP Washable Wall& Quarry TileC/T 3,240 sI2.00 d3Gas, Grease Trap& Suppression…C/T 4,815 sI1.00 d4StainlessAppliances…C/T 3,600 sI0.67 d5Gas Engineer &Electrical PAT…C/T 2,430 sI0.83 dCUSTOMERUniversities &Event Venues6 / modules

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Insulated Steel Box Weld2,925 s35 min93%98.2%58 (1.33 d)8
2. FRP Washable Wall & Quarry Tile3,240 s20 min94%97.6%37 (1.17 d)7
3. Gas, Grease Trap & Suppression Pipe4,815 s30 min86%93.0%212 (2.00 d)4
4. Stainless Appliances Lock-Down3,600 s15 min94%97.2%26 (1.00 d)6
5. Gas Engineer & Electrical PAT Cert2,430 s10 min97%99.1%24 (0.67 d)10

Key figures

Takt time
4,500 s
Lead time
7.63 d
Value-added time
17,010 s
Process cycle efficiency (PCE)
8.3%
Rolled throughput yield (RTY)
85.9%
Customer demand per day
6 modules
Line capacity per day
4 modules
Bottleneck
Gas, Grease Trap & Suppression Pipe

Reading the bottleneck

The bottleneck is "Gas, Grease Trap & Suppression Pipe": it can process 4 modules per day against a demand of 6 modules, so it falls short of demand by 40.2%. Once downtime and scrap are counted, its cycle time grows from 4,815 s to 6,020 s, against a takt of 4,500 s. The largest loss at this step is changeovers (30 min every 2 units), about 900 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.

Other scenarios in this family

More scenarios of Modular Construction & Offsite Prefab: Modular Construction & Offsite Prefab