Offsite Prefabricated Tiled Bathroom Wet-Pod

Product family: Turnkey Hotel/Hospital Pods.

Flow: Sanitary Fittings & Ceramic Tiles → GRC Waterproof Base Tray Pour → Steel Frame & Plumbing First Fix → Board Sheath, Tile & Grout → Vanity, Mirror, Toilet & LED → 3-Bar Leak Test & Poly Shrink → Multi-Family & Hotel Builders

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Offsite Prefabricated Tiled Bathroom Wet-PodSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Sanitary Fittings & Ceramic Tiles → GRC Waterproof Base Tray Pour (1,254 s) → Steel Frame & Plumbing First Fix (1,389 s) → Board Sheath, Tile & Grout (2,064 s) → Vanity, Mirror, Toilet & LED (1,543 s) → 3-Bar Leak Test & Poly Shrink (1,041 s) → Multi-Family & Hotel Builders.SUPPLIERSanitaryFittings &Ceramic TilesI1.39 d1GRC WaterproofBase Tray PourC/T 1,254 sI1.21 d2Steel Frame &Plumbing First…C/T 1,389 sI2.00 d3Board Sheath,Tile & GroutC/T 2,064 sI1.00 d4Vanity, Mirror,Toilet & LEDC/T 1,543 sI0.61 d53-Bar Leak Test &Poly ShrinkC/T 1,041 sI0.79 dCUSTOMERMulti-Family &Hotel Builders28 / modules

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. GRC Waterproof Base Tray Pour1,254 s35 min93%98.2%2239 (1.39 d)37
2. Steel Frame & Plumbing First Fix1,389 s20 min94%97.6%1434 (1.21 d)34
3. Board Sheath, Tile & Grout2,064 s30 min86%93.0%1156 (2.00 d)19
4. Vanity, Mirror, Toilet & LED1,543 s15 min94%97.2%828 (1.00 d)30
5. 3-Bar Leak Test & Poly Shrink1,041 s10 min97%99.1%717 (0.61 d)48

Key figures

Takt time
1,929 s
Lead time
7.14 d
Value-added time
7,291 s
Process cycle efficiency (PCE)
1.9%
Rolled throughput yield (RTY)
85.9%
Customer demand per day
28 modules
Line capacity per day
19 modules
Bottleneck
Board Sheath, Tile & Grout

Reading the bottleneck

The bottleneck is "Board Sheath, Tile & Grout": it can process 19 modules per day against a demand of 28 modules, so it falls short of demand by 31.6%. Once downtime and scrap are counted, its cycle time grows from 2,064 s to 2,581 s, against a takt of 1,929 s. The largest loss at this step is equipment downtime (uptime 86%), about 336 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.