Offsite Prefab Building Modules
Product family: Volumetric Residential Modules.
Flow: Structural Steel & MEP Wholesalers → Chassis Framing → Envelope & Insulation → MEP Rough-In & Test → Interior Fit-Out → QA Sign-Off & Wrap → Site General Contractors
No account needed. Change any value and the indicators update.
Value stream map
Process steps
| Step | Cycle time | Changeover | Uptime | Yield | Batch | Stock before | Capacity per day |
|---|---|---|---|---|---|---|---|
| 1. Chassis Framing | 1,755 s | 35 min | 93% | 98.2% | 8 | 14 (1.40 d) | 13 |
| 2. Envelope & Insulation | 1,944 s | 20 min | 94% | 97.6% | 5 | 12 (1.20 d) | 12 |
| 3. MEP Rough-In & Test | 2,889 s | 30 min | 86% | 93.0% | 4 | 20 (2.00 d) | 6 |
| 4. Interior Fit-Out | 2,160 s | 15 min | 94% | 97.2% | 3 | 10 (1.00 d) | 10 |
| 5. QA Sign-Off & Wrap | 1,458 s | 10 min | 97% | 99.1% | 3 | 6 (0.60 d) | 16 |
Key figures
- Takt time
- 2,700 s
- Lead time
- 7.38 d
- Value-added time
- 10,206 s
- Process cycle efficiency (PCE)
- 5.1%
- Rolled throughput yield (RTY)
- 85.9%
- Customer demand per day
- 10 modules
- Line capacity per day
- 6 modules
- Bottleneck
- MEP Rough-In & Test
Reading the bottleneck
The bottleneck is "MEP Rough-In & Test": it can process 6 modules per day against a demand of 10 modules, so it falls short of demand by 37.7%. Once downtime and scrap are counted, its cycle time grows from 2,889 s to 3,612 s, against a takt of 2,700 s. The largest loss at this step is equipment downtime (uptime 86%), about 470 s per unit. Reducing that loss is where the first improvement test belongs.
The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.
Other scenarios in this family
More scenarios of Modular Construction & Offsite Prefab: Modular Construction & Offsite Prefab
- Offsite Prefabricated Tiled Bathroom Wet-Pod
- Automated Gang-Nail Timber Roof Truss Line
- Unitized Curtain-Wall Aluminum-Glass Facade
- Multi-Service Prefab Corridor & Riser Rack
- 45m Precast Prestressed Concrete Bridge Girder
- Turnkey BSL-3 / GMP Modular Cleanroom Pod
- Carousel Automated Hollowcore & Sandwich Wall
- 80m Clear-Span Roof Structural Steel Truss
- Commercial Prefab Containerized Kitchen Pod
- Expandable Solar-Powered Mobile Clinic Unit
- Custom Acoustic Architectural Precast Stair Flight