Offsite Prefab Building Modules

Product family: Volumetric Residential Modules.

Flow: Structural Steel & MEP Wholesalers → Chassis Framing → Envelope & Insulation → MEP Rough-In & Test → Interior Fit-Out → QA Sign-Off & Wrap → Site General Contractors

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Offsite Prefab Building ModulesSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Structural Steel & MEP Wholesalers → Chassis Framing (1,755 s) → Envelope & Insulation (1,944 s) → MEP Rough-In & Test (2,889 s) → Interior Fit-Out (2,160 s) → QA Sign-Off & Wrap (1,458 s) → Site General Contractors.SUPPLIERStructuralSteel & MEPWholesalersI1.40 d1Chassis FramingC/T 1,755 sI1.20 d2Envelope &InsulationC/T 1,944 sI2.00 d3MEP Rough-In &TestC/T 2,889 sI1.00 d4Interior Fit-OutC/T 2,160 sI0.60 d5QA Sign-Off &WrapC/T 1,458 sI0.80 dCUSTOMERSite GeneralContractors10 / modules

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Chassis Framing1,755 s35 min93%98.2%814 (1.40 d)13
2. Envelope & Insulation1,944 s20 min94%97.6%512 (1.20 d)12
3. MEP Rough-In & Test2,889 s30 min86%93.0%420 (2.00 d)6
4. Interior Fit-Out2,160 s15 min94%97.2%310 (1.00 d)10
5. QA Sign-Off & Wrap1,458 s10 min97%99.1%36 (0.60 d)16

Key figures

Takt time
2,700 s
Lead time
7.38 d
Value-added time
10,206 s
Process cycle efficiency (PCE)
5.1%
Rolled throughput yield (RTY)
85.9%
Customer demand per day
10 modules
Line capacity per day
6 modules
Bottleneck
MEP Rough-In & Test

Reading the bottleneck

The bottleneck is "MEP Rough-In & Test": it can process 6 modules per day against a demand of 10 modules, so it falls short of demand by 37.7%. Once downtime and scrap are counted, its cycle time grows from 2,889 s to 3,612 s, against a takt of 2,700 s. The largest loss at this step is equipment downtime (uptime 86%), about 470 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.