Custom Acoustic Architectural Precast Stair Flight

Product family: Terrazzo Grind Concrete Stairs.

Flow: Marble Aggregate & Rebar → Hydraulic Adjustable Stair Form → Acoustic Nosing Insert & Mesh → High-Frequency Vib Concrete Pour → Diamond Terrazzo Tread Polish → Lifting Loop Test & A-Frame → Residential & Office Towers

Open this map in the free editor

No account needed. Change any value and the indicators update.

Value stream map

Value stream map: Custom Acoustic Architectural Precast Stair FlightSupplier on the left, customer on the right, process steps in between with their cycle time, and a stock triangle with days of stock before each step. Marble Aggregate & Rebar → Hydraulic Adjustable Stair Form (731 s) → Acoustic Nosing Insert & Mesh (810 s) → High-Frequency Vib Concrete Pour (1,204 s) → Diamond Terrazzo Tread Polish (900 s) → Lifting Loop Test & A-Frame (608 s) → Residential & Office Towers.SUPPLIERMarbleAggregate &RebarI1.42 d1HydraulicAdjustable Stair…C/T 731 sI1.21 d2Acoustic NosingInsert & MeshC/T 810 sI2.00 d3High-FrequencyVib Concrete PourC/T 1,204 sI1.00 d4Diamond TerrazzoTread PolishC/T 900 sI0.58 d5Lifting Loop Test& A-FrameC/T 608 sI0.79 dCUSTOMERResidential &Office Towers24 / parts

Process steps

StepCycle timeChangeoverUptimeYieldBatchStock beforeCapacity per day
1. Hydraulic Adjustable Stair Form731 s35 min93%98.2%1934 (1.42 d)30
2. Acoustic Nosing Insert & Mesh810 s20 min94%97.6%1229 (1.21 d)28
3. High-Frequency Vib Concrete Pour1,204 s30 min86%93.0%1048 (2.00 d)15
4. Diamond Terrazzo Tread Polish900 s15 min94%97.2%724 (1.00 d)24
5. Lifting Loop Test & A-Frame608 s10 min97%99.1%614 (0.58 d)39

Key figures

Takt time
1,125 s
Lead time
7.16 d
Value-added time
4,253 s
Process cycle efficiency (PCE)
2.2%
Rolled throughput yield (RTY)
85.9%
Customer demand per day
24 parts
Line capacity per day
15 parts
Bottleneck
High-Frequency Vib Concrete Pour

Reading the bottleneck

The bottleneck is "High-Frequency Vib Concrete Pour": it can process 15 parts per day against a demand of 24 parts, so it falls short of demand by 37.2%. Once downtime and scrap are counted, its cycle time grows from 1,204 s to 1,505 s, against a takt of 1,125 s. The largest loss at this step is equipment downtime (uptime 86%), about 196 s per unit. Reducing that loss is where the first improvement test belongs.

The figures on this page are illustrative starting values to be replaced with your own measurements. They are not industry benchmarks.

Other scenarios in this family

More scenarios of Modular Construction & Offsite Prefab: Modular Construction & Offsite Prefab